Key Facts

Adopted code
2022 California Electrical Code (Title 24, Part 3)
Plan review fee
100% of building permit fee
Underground service
required for new buildings, § 15.12.030
Temporary power
pole required; generators prohibited, § 15.12.040
Fee authority
set by City Council resolution

Summary

In the City of Gardena, all electrical work follows the 2022 California Electrical Code, adopted by reference at § 15.12.010, and every permit is charged at the fee set by City Council resolution with a plan-review fee equal to 100 percent of the permit fee under § 15.12.020. New buildings must also run electrical and communications service underground rather than overhead.

§ 15.12.010. Adoption of electrical code. Except as may otherwise be provided in this title, the California Electrical Code, 2022 Edition (Part 3 of Title 24 of the California Code of Regulations), without any appendices, is hereby adopted by reference and made a part of this chapter as though set forth in full herein. ... § 15.12.020. Fees. ... Section 89.108.4.2 of the 2022 California Electrical Code is hereby amended to read as follows: 89.108.4.2 Fees. The fee for each permit shall be as set forth in the latest resolution adopted by the City Council. When a plan or other data are required to be submitted by this Code, a plan review fee shall be paid at the time of submitting plans and specifications for review. Said plan review fee shall be one hundred (100) percent of the building permit fee.

Full Breakdown

Gardena Municipal Code § 15.12.010 adopts the 2022 California Electrical Code, Part 3 of Title 24 of the California Code of Regulations, without any appendices, as the electrical code of the city. Section 15.12.020 amends the code's fee section, 89.108.4.2, so that every electrical permit fee is set by the latest City Council resolution and the plan-review fee equals 100 percent of the building permit fee; the section spells out how fees are counted for new branch circuits, added outlets, motors, transformers, service sections and switchboard sections, down to counting three-phase lighting circuits as two branch circuits.

The chapter also amends CEC Section 230.30 at § 15.12.030 to require new buildings and structures to install underground electrical and communications service laterals rather than overhead lines, and requires existing overhead service to go underground when new dwelling units are added and the expansion exceeds 50 percent of the existing floor area or 50 percent of the structure's value, unless Southern California Edison certifies in writing that undergrounding is infeasible. Streets that already have underground service, or that never had overhead lines before July 1, 1977, must stay underground permanently.

Section 15.12.040 further requires every construction site without electrical service to install a temporary power pole before a building permit issues, and bars generators as a substitute.

Violations & Fines

Performing electrical work without the required permit, or supplying a site with a generator instead of the required temporary power pole under § 15.12.040, is a Building Code violation under § 15.06.050 and § 1.16.010. Starting electrical work before the permit issues quadruples the permit and plan-review fee under the fee-computation method in § 15.06.040(B), and the violation can be charged as a misdemeanor, punishable by a fine of up to $1,000 and up to six months in jail, or as a graduated infraction with fines rising to $1,000 for repeat local building-code violations within a year.

Frequently Asked Questions

What electrical code does Gardena enforce?
The 2022 California Electrical Code, Part 3 of Title 24, adopted without appendices by § 15.12.010. It comprises the electrical code of the city, and every wiring, service or equipment permit is reviewed against that edition by the Building Division.
How much does an electrical permit plan review cost in Gardena?
Under § 15.12.020, the plan-review fee is 100 percent of the building permit fee, and the permit fee itself is set by the latest resolution the City Council adopts, not by a fixed amount printed in the code.
Does Gardena require new electrical service to run underground?
Yes. Section 15.12.030 requires new buildings to install underground electrical and communications laterals, and requires existing overhead service to be moved underground when added dwelling units push a remodel past 50 percent of the building's floor area or value, unless Edison certifies undergrounding is infeasible.

Sources & Official References

Other rules in Gardena

All Gardena rules

California rules heatmap·Compare Gardena to another location·View the California building safety overview

Get notified when Electrical Permits in Gardena, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Los Angeles County handle electrical permits.

Long Beach, CA
Some Restrictions
Carson, CA
Some Restrictions
West Covina, CA
Some Restrictions
El Monte, CA
Some Restrictions
Los Angeles, CA
Some Restrictions
Compton, CA
Some Restrictions
Pasadena, CA
Some Restrictions
Lancaster, CA
Some Restrictions