Lafayette, IN Building Safety: Electrical Permits (2026)
Key Facts
- Permit required before wiring
- Yes, City Engineer (§13.02.040(A))
- Fee, single-family/duplex
- $50.00
- Fee, multifamily/commercial/industrial
- $200.00
- Adopted code
- Indiana Electrical Code, 1984 ed. (675 IAC 17)
- Local inspector
- City Electrician (Electric Inspector)
- Max fine
- $1,000 per day (§13.02.990)
Summary
In the City of Lafayette, Indiana, wiring a building for electric current requires a permit from the City Engineer before work starts, under Section 13.02.040(A). The filing fee is $50.00 for single-family and duplex residential wiring and $200.00 for multifamily, commercial, or industrial work, and all wiring must meet the Indiana Electrical Code.
A.Before the wiring of any building within the city for the transmission of electric current is done, the person doing such work shall first obtain a permit therefor.B.Application for the permit required by subsection A of this section shall be in writing on blanks provided for the purpose, and filed with the City Engineer. ... D.The filing fee for an electric only permit shall be: Single family and duplex residential $50.00 Multifamily residential, commercial, industrial $200.00
Full Breakdown
Section 13.02.040(A) makes it unlawful to wire any building in the City of Lafayette for the transmission of electric current before the person doing the work obtains a permit. The written application goes to the City Engineer on the city's forms and must state the site of the building, the lot number, the addition name if applicable, the street name, and the intended use of the premises, per Section 13.02.040(B); a copy of the plans and specifications for the wiring must also be submitted before the permit can issue, under Section 13.02.040(C).
The filing fee is $50.00 for a single-family or duplex residential electric-only permit and $200.00 for multifamily residential, commercial, or industrial work, per Section 13.02.040(D). All electrical work must conform to the Indiana Electrical Code, the 1984 edition of the National Electrical Code as adopted and amended by the state at 675 IAC Article 17, under Section 13.02.010. The City Electrician serves as the city's Electric Inspector under Section 13.02.020, and the Inspector has the right to enter any building or manhole at any time to test electrical apparatus, on application to the owner or person in charge, under Section 13.02.030.
Anyone doing electrical work who is not already bonded to the city must also post a bond, separate from the concrete, plumbing, and general contractor bond amounts set in Section 13.01.060(C).
Violations & Fines
Wiring a building without the Section 13.02.040(A) permit, or wiring found defective or dangerous under Section 13.02.070, lets the Electric Inspector order the owner or occupant to make repairs; if the required work is not completed within ten days, or any longer period stated in the Section 13.02.080 notice, Section 13.02.090 lets the Inspector disconnect electric service to the building. Any violation of the electricity chapter carries a fine of up to $1,000.00 under Section 13.02.990, with each day a separate offense.
Frequently Asked Questions
Do I need a permit before wiring a building in the City of Lafayette?
How much does an electrical permit cost in Lafayette, Indiana?
What electrical code does the City of Lafayette enforce?
Sources & Official References
Other rules in Lafayette
Compare Lafayette to another location·View the Indiana building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.