Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Enforcing official
Electrical Subcode Official
Base fixture fee
$75 for first 25 receptacles/fixtures
Plan review surcharge
20% of subcode fee
Permit update fee
$100/hour per subcode
Governing sections
§§ 108-1A, 108-4D

Summary

Old Bridge Township requires an electrical subcode permit for wiring work, enforced by the Electrical Subcode Official within the Division of Code Enforcement under § 108-1. Section 108-4D prices electrical work item by item, starting at $75 for the first 25 receptacles or fixtures.

There is hereby established in the Township of Old Bridge a State Uniform Construction Code enforcing agency, to be known as the "Division of Code Enforcement in the Department of Community Development," consisting of a Construction Official, Building Subcode Official, Plumbing Subcode Official, Fire Protection Subcode Official, Electrical Subcode Official and such other subcode officials for such additional subcodes as the Commissioner of the Department of Community Affairs, State of New Jersey, shall hereafter adopt as part of the State Uniform Construction Code. ... Electrical subcode fees. (1) Receptacles and fixtures: (a) First 25: $75. (b) Each additional 25 up to 150: $40. (c) Each additional 25 over 150: $75.

Full Breakdown

The Old Bridge Township Code creates an Electrical Subcode Official position within the Division of Code Enforcement under § 108-1A, one of five subcode officials, alongside Building, Plumbing, Fire Protection and the Construction Official, that make up the Township's State Uniform Construction Code enforcing agency. That official reviews and inspects electrical work under separate fees set out in § 108-4D, last revised by Ordinance No. 2026-10 on April 28, 2026. Electrical subcode fees are itemized by the type and quantity of equipment rather than charged as a flat percentage: receptacles and fixtures cost $75 for the first 25, $40 for each additional 25 up to 150, and $75 for each additional 25 beyond that.

Motors and electrical devices are billed on a horsepower scale, from $75 for units over 1 HP up to 10 HP, rising to $450 for anything larger than 100 HP, and transformers and generators are billed on a similar kilowatt scale starting at $60. As with the other subcodes, every electrical application is subject to the Township's 20% plan review fee under § 108-4A(5), which is not refundable once paid, and permit-update reviews of an already-approved plan cost $100 per hour per subcode under § 108-4A(6).

The fee must be paid, along with the building and any other applicable subcode fees, before the Division of Code Enforcement will issue the combined construction permit, since § 108-4 treats the overall permit fee as the sum of the subcode fees below.

Violations & Fines

Electrical work performed without the required subcode permit and inspection by the Electrical Subcode Official is enforced under § 108-1 and, absent a specific electrical penalty in Chapter 108, defaults to the Township's general penalty in § 1-3: up to $1,250 in fines, up to 90 days in jail, or up to 90 days of community service.

Frequently Asked Questions

Who inspects electrical permits in Old Bridge?
The Electrical Subcode Official, one of the subcode officials established within the Division of Code Enforcement under § 108-1 of the Township Code as part of the State Uniform Construction Code enforcing agency.
How much does an electrical permit cost for a small job?
Section 108-4D(1) charges $75 for the first 25 receptacles or fixtures, $40 for each additional 25 up to 150, and $75 for each additional 25 beyond 150, on top of any applicable plan review fee.
Are motors and generators charged differently than outlets?
Yes. Section 108-4D bills motors and electrical devices on a horsepower scale starting at $75 for units over 1 HP, and transformers and generators on a kilowatt scale starting at $60, separate from the receptacle and fixture fees.

Sources & Official References

Other rules in Old Bridge

All Old Bridge rules

Compare Old Bridge to another location·View the New Jersey building safety overview

Get notified when Electrical Permits in Old Bridge, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in this county handle electrical permits.

Edison, NJ
Some Restrictions