Key Facts
- First block (1-50 devices) fee
- $55
- Each additional block (25 devices)
- $15
- Minimum electrical permit fee
- $55
- Equipment up to 225 amperes
- $65 per item
- Equipment over 1,000 amperes
- $425 per item
Summary
Electrical work in the City of Vineland requires an electrical subcode permit priced in blocks of fixtures and devices. The first block of up to 50 receptacles, fixtures or devices costs $55, each additional block of 25 costs $15, and every electrical permit carries a $55 minimum fee.
The electrical subcode fees shall be: ... For the first block, consisting of one to 50 receptacles, fixtures or devices, the fee shall be $55. ... For each additional block, consisting of up to 25 receptacles, fixtures or devices, the fee shall be $15. ... The minimum electrical subcode fee shall be $55.
Full Breakdown
Under City Code § 300-3A(3), the City of Vineland charges electrical subcode fees on a block basis for receptacles, fixtures and devices such as lighting fixtures, wall switches, smoke and heat detectors, alarm devices and similar fixtures rated 20 amperes or less. The first block, covering one to 50 such items, is billed $55, and each additional block of up to 25 items adds $15. Larger equipment is billed individually: motors and transformers rated one to 10 horsepower or kilowatt cost $15 each, service equipment and panel boards rated up to 225 amperes cost $65, equipment from 225 to 1,000 amperes costs $125, and anything larger costs $425.
Multimeter stacks are billed on the ampere rating of the main bus rather than the number of meters. Every electrical permit, regardless of scope, carries a $55 minimum subcode fee, and public swimming pools require a $75 annual electrical inspection. These fees are collected by the Construction Enforcement Agency within the Department of Licenses and Inspections as part of the overall construction permit required before electrical work begins, alongside the building, plumbing, fire protection and mechanical subcode fees set in the same section.
Violations & Fines
Performing electrical work covered by the Uniform Construction Code without first obtaining the electrical subcode permit is enforceable under the City's general penalty ordinance, § 1-15, in Vineland Municipal Court: a fine of $100 to $2,000, up to 90 days in the Cumberland County Jail, or up to 90 days of community service.
Frequently Asked Questions
How is an electrical permit priced in Vineland?
What counts toward the 50-device first block?
How much does a large service panel permit cost?
Sources & Official References
Other rules in Vineland
Compare Vineland to another location·View the New Jersey building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.