Skip to main content
CityRuleLookup

Westminster, CO Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
National Electrical Code, state-amended
Adoption section
Municipal Code § 11-9-1(b)(3)
Permit requirement
Municipal Code § 11-9-3(A)(1)
Service disconnect rule
Outdoor location, never inside dwelling
Unpermitted work penalty
$250 minimum, doubled fee

Summary

Westminster adopts the National Electrical Code, as amended by the Colorado State Electrical Board, as its Electrical Code under Section 11-9-1(b)(3), and any electrical system work needs a building permit under Section 11-9-3(A)(1). Only a short list of minor work, like reinstalling a plug receptacle or repairing a broken switch, is exempt from that permit under Section 11-9-3(A)(2).

Electrical: (a)Listed cord-and-plug connected temporary decorative lighting.(b)Reinstallation of attachment plug receptacles but not the outlets therefor.(c)Replacement of branch circuit overcurrent devices of the required capacity in the same location.(d)Electrical wiring, devices, appliances, apparatus or equipment operating at less than 25 volts and not capable of supplying more than 50 watts of energy.(e)Repair of broken or defective electrical receptacles, switches, or lamps.(f)Connection of approved portable electrical equipment to approved permanently installed receptacles.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 12).

Full Breakdown

Section 11-9-1(b)(3) adopts "the National Electrical Code, sponsored by the National Fire Protection Association, Quincy, Massachusetts, as adopted by the State of Colorado State Electrical Board and as may be amended from time to time," as the City's Electrical Code. Section 11-9-3(A)(1) folds electrical work into the general permit requirement, making it unlawful to "construct, install, enlarge, alter, repair, move, improve, remove, replace, convert, demolish, equip, or change the occupancy of any ... electrical system" without a permit from the Building Official.

Section 11-9-3(A)(2) carves out only narrow electrical exceptions: "Listed cord-and-plug connected temporary decorative lighting," "Reinstallation of attachment plug receptacles but not the outlets therefor," "Replacement of branch circuit overcurrent devices of the required capacity in the same location," wiring "operating at less than 25 volts and not capable of supplying more than 50 watts," "Repair of broken or defective electrical receptacles, switches, or lamps," and connecting approved portable equipment to existing receptacles. Everything else, including new circuits, panel upgrades, service changes, and EV charger installations, needs a permit and inspection. Section 11-9-7 also locally amends NEC Article 230.70(A)(1) to require the service disconnect at a readily accessible outdoor location, never inside a residential dwelling unit, with an exception for a garage disconnect mounted back-to-back with the meter.

Violations & Fines

Doing electrical work without the required permit doubles the eventual permit fee to a minimum of $250.00 for a first offense and $500.00 for later offenses under Section 11-9-3(E)(5), and a third offense can cost the contractor their City registration. Working under a suspended or revoked permit, or violating the adopted Electrical Code generally, is a misdemeanor under Section 1, Chapter 8, Title I.

Frequently Asked Questions

What electrical work is exempt from a permit in Westminster?
Section 11-9-3(A)(2) exempts only minor items: temporary decorative lighting, reinstalling plug receptacles, replacing branch circuit overcurrent devices of the same capacity, low-voltage wiring under 25 volts and 50 watts, and repairing broken receptacles, switches, or lamps. New circuits and service work need a permit.
Where must my electrical service disconnect be located in Westminster?
Section 11-9-7 requires the service disconnecting means at a readily accessible outdoor location; no disconnect may be installed inside a residential dwelling unit. The only exception allows a garage-mounted disconnect placed back-to-back with the meter.
What NEC edition does Westminster enforce?
Section 11-9-1(b)(3) adopts the National Electrical Code as adopted and amended from time to time by the State of Colorado State Electrical Board, rather than naming a fixed local edition, so the state-current NEC version governs electrical permits.

Sources & Official References

Other rules in Westminster

All Westminster rules

Compare Westminster to another location·View the Colorado building safety overview

Get notified when Electrical Permits in Westminster, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Adams County handle electrical permits.

Thornton, CO