Fairfield, CA Building Safety: Green Building Code (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
2025 CalGreen, Title 24 Part 11
Diversion target
65% of construction/demolition waste
Plan required
Waste Reduction and Recycling Plan pre-permit
Small-project exemption
999 sq ft or less
Non-compliance deposit
3% of project value, up to $10,000

Summary

Fairfield adopts the 2025 California Green Building Standards Code (CalGreen) under Municipal Code § 5.2.15, then layers on its own construction and demolition waste program in § 9.460 requiring 65% diversion from landfill. Most permitted construction, demolition, and qualifying additions must file a Waste Reduction and Recycling Plan before a permit issues, backed by a deposit of up to $10,000 for non-compliant applicants.

Adopt the California Green Building Standards Code, 2025 edition, as adopted and amended by the California Building Standards Commission in the California Building Standards Code, California Code of Regulations, title 24, part 11. ... Construction and Demolition Waste generated from applicable construction, remodeling, or demolition projects shall be diverted from disposal to landfills through recycling, reuse and diversion programs to meet the current required diversion as described in the California Green Building Standards Code, adopted pursuant to Chapter 5, section 5.2.14 of this Code, which is 65% diversion as of 2021.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4962673; v0 updated 2026-02-17).

Full Breakdown

15 adopts CalGreen, 2025 edition, Title 24, Part 11, as amended by the California Building Standards Commission. 460 requires construction and demolition waste from applicable projects to be diverted from landfill disposal through recycling, reuse, and diversion programs to meet the CalGreen diversion rate, set at 65% as of 2021, with separate calculations for the construction and demolition portions of a job. 480 exempts emergency work, hazardous-waste-contaminated projects, and demolitions or additions of 999 square feet or less. 490, no building or demolition permit issues without an approved Waste Reduction and Recycling Plan, unless the applicant instead contracts with an Authorized C&D Collector and provides that contract to the City Manager.

If a project isn't hitting the 65% diversion target, or hasn't submitted required quarterly reports, the City may require a deposit of 3% of total project value, capped at $10,000; five consecutive compliant projects are required to shed that deposit condition after a non-compliance finding.

Violations & Fines

Collecting construction and demolition waste without an approved Construction and Demolition Waste Collection Agreement is a violation of Chapter 9. The City notifies the responsible person by mail, email, or personal service and gives 24 hours to remove any collection containers; failing to apply for an agreement and remove containers within that window lets City staff begin abatement under § 27.401(r). Non-compliant applicants also face a deposit of 3% of project value, up to $10,000, on their current project and on the next five projects after a formal non-compliance determination.

Frequently Asked Questions

Do I need a waste plan for a small remodel in Fairfield?
Not if the addition, alteration, or demolition is 999 square feet or less; § 9.480 exempts those projects. Larger permitted construction, demolition, and qualifying additions or alterations need an approved Waste Reduction and Recycling Plan before a permit issues.
How much construction waste does Fairfield require me to divert?
65%, the CalGreen diversion rate set as of 2021 under § 9.460. Separate diversion calculations, plans, and reports are required for the construction portion and the demolition portion of a project.
What happens if my project misses the diversion target?
The City can require a deposit of 3% of the total project value, capped at $10,000, if you're not hitting 65% diversion or haven't submitted required quarterly reports, and that deposit condition can follow you onto your next five projects after a non-compliance finding.

Sources & Official References

Other rules in Fairfield

All Fairfield rules

California rules heatmap·Compare Fairfield to another location·View the California building safety overview

Get notified when Green Building Code in Fairfield, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Green Building Code in Nearby Cities

How other cities in Solano County handle green building code.

Vacaville, CA
Some Restrictions
Vallejo, CA
Some Restrictions