Key Facts

Governing standard
CALGreen, 24 CCR Part 11; stricter rule controls
Multifamily trigger
Five or more dwelling units on a building site
Commercial trigger
New construction or additions over 30% of floor area
C&D diversion standard
50% of total wastes generated
Diversion deposit
Lesser of three percent of project cost or $10,000.00
Building Code adoption
2025 California Building Standards Code, § 15.04.010

Summary

In the City of Paramount, anyone applying for a permit for new construction, additions or alterations covered by CALGreen must comply with Municipal Code § 13.09.090 and the California Green Building Standards Code, and the more stringent requirement controls. Projects must include recycling and organics storage areas and meet the City's construction and demolition debris rules.

A. Persons applying for a permit from the City for new construction and building additions and alterations shall comply with the requirements of this section and all required components of the California Green Building Standards Code, 24 CCR, Part 11, known as CALGreen, as amended, if its project is covered by the scope of CALGreen. If the requirements of CALGreen are more stringent than the requirements of this section, the CALGreen requirements shall apply. ... B. For projects covered by CALGreen or more stringent requirements of the City, the applicants must, as a condition of the City's permit approval, comply with the following: ... 3. Comply with CALGreen requirements and applicable law related to management of C&D, including diversion of organic waste in C&D from disposal. Comply with the City's C&D regulations, Section 13.20.780 of this Code, and all written and published City policies and/or administrative guidelines regarding the collection, recycling, diversion, tracking, and/or reporting of C&D.

Full Breakdown

Section 13.09.090 ties permit approval in the City of Paramount to the California Green Building Standards Code, 24 CCR, Part 11, known as CALGreen. It applies to persons applying for a permit for new construction and building additions and alterations covered by CALGreen's scope, and where CALGreen is more stringent than the section, CALGreen controls. Section 15.04.010 separately adopts the 2025 California Building Standards Code, including the California Green Building Standards Code, as the Building Code of the City of Paramount, with Ordinance 1208 dated 11/18/2025.

As a condition of permit approval, a project with five or more multifamily dwelling units on a building site must provide readily accessible areas serving all buildings for storage and collection of blue, green and three-plus container materials, or provide adequate recycling space under CALGreen Sections 4.408.1, 4.410.2, 5.408.1 and 5.410.1. New commercial construction or additions resulting in more than 30% of the floor area carry the same obligation. Every covered project must also follow CALGreen and applicable law on construction and demolition debris, including diversion of organic waste, and the City's C&D regulations in § 13.20.780.

Section 13.20.780 sets a 50% waste diversion standard. Projects exempt from the deposit, fee and reporting requirements include single-family homes up to two units not part of a greater planned development, construction projects of $100,000.00 or less in value, projects under 1,000 square feet, work needing only a plumbing, electrical or mechanical permit, and work treating or removing hazardous or toxic materials. Under § 13.20.790 the diversion deposit is the lesser of three percent of total project cost or $10,000.00, and § 13.20.780 waives the deposit when the applicant uses the City's franchised waste hauler. Section 13.09.100 adds MWELO compost and mulch rules for new landscape area greater than 500 square feet.

Violations & Fines

A violation of Chapter 13.09 in the City of Paramount draws a notice of violation and administrative citation: $50.00 to $100.00 for a first violation, $100.00 to $200.00 for a second, and $250.00 to $500.00 for a third or subsequent, after a 60-day compliance notice. On a C&D project, the diversion deposit is refunded in full at 50% diversion and otherwise pro rated on the percent of diversion attained, and only if a good faith effort is documented.

Frequently Asked Questions

Does CALGreen apply to my permit in the City of Paramount?
Section 13.09.090 applies to persons applying for a permit for new construction and building additions and alterations, if the project is covered by the scope of CALGreen. Where CALGreen is more stringent than the section, the CALGreen requirement applies. Section 15.04.010 adopts the 2025 California Green Building Standards Code as part of the City's Building Code.
What recycling space must a project provide?
A site with five or more multifamily dwelling units, and new commercial construction or additions resulting in more than 30% of the floor area, must provide readily accessible areas for storage and collection of blue, green and three-plus container materials, or comply with adequate recycling space under CALGreen Sections 4.408.1, 4.410.2, 5.408.1 and 5.410.1.
What diversion rate is required for construction waste?
Section 13.20.780 requires all construction and demolition projects to achieve the maximum feasible diversion but not less than the performance standard of 50% of the total wastes generated. Documentation must rest on weight receipts or other documentation the City approves, and a project can show a good faith effort to meet the standard.
How big is the diversion deposit, and who is exempt?
Under § 13.20.790 the deposit is the lesser of three percent of total project cost or $10,000.00, and no deposit is required when the applicant uses the City's franchised waste hauler. Exempt categories include single-family homes up to two units, projects of $100,000.00 or less, projects under 1,000 square feet, and plumbing, electrical or mechanical only work.

Sources & Official References

Other rules in Paramount

All Paramount rules

California rules heatmap·Compare Paramount to another location·View the California building safety overview

Get notified when Green Building Code in Paramount, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Green Building Code in Nearby Cities

How other cities in Los Angeles County handle green building code.

South Gate, CA
Light Restrictions
Downey, CA
Some Restrictions
El Monte, CA
Some Restrictions
Long Beach, CA
Some Restrictions
Carson, CA
Some Restrictions
Santa Clarita, CA
Some Restrictions
Pasadena, CA
Some Restrictions
Palmdale, CA
Some Restrictions