Key Facts

Benefit
Expedited plan review, not a mandate
Qualifying programs
LEED, EarthCraft House, ENERGY STAR
Required paperwork
Registration proof plus credit checklist
Administering official
Director of sustainability (CDRA director)
Adopted
Ord. No. 2020-020, § 1, 7-28-2020

Summary

South Fulton's Green Building Community Incentives chapter (Title 14, Ch. 13) sets no green building mandate. Instead it rewards builders who pursue LEED, EarthCraft House, or ENERGY STAR certification with expedited plan review, provided they submit proof of registration and a program checklist showing which credits they plan to pursue.

(1)Green building:a.Several different certification programs exist to rate the sustainability of a building. One such standard is the Unites States Green Building Council's Leadership in Energy and Environmental Design (LEED) rating system. Additionally, the Environmental Protection Agency and United States Department of Energy's EnergyStar and EarthCraft programs include guidelines for buildings that are not LEED certified.b.Builders seeking green building certification(s) including LEED, EarthCraft, and ENERGY STAR must submit proof of LEED, EarthCraft House or ENERGY STAR registration and the corresponding program's checklist indicating all of the credits they plan to pursue. Additionally, intentions must be shown on building plans and indicated on their building permit application in order to be granted expedited plan review.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 13 Update 1).

Full Breakdown

Adopted by Ord. No. 2020-020, § 1 on July 28, 2020, Chapter 13 recognizes four voluntary sustainability paths: green building certification, solar energy, WaterSense water efficiency, and pervious paving, each earning the same reward, expedited plan review for new construction and renovations (Sec. 14-13001). For the certification path, builders seeking LEED, EarthCraft, or ENERGY STAR status must submit proof of program registration and the certifying body's credit checklist, and must show that intent on the building plans and the permit application itself (Sec. 14-13003(1)). The director of community development and regulatory affairs doubles as the city's director of sustainability and works with the chief building official and other department heads to make sure expedited review is actually applied to qualifying projects (Sec.

14-13005). The city's promise has a limit: Sec. 14-13004 warns that expedited review 'is not always practicable' when a project also needs sign-off from outside agencies, and the city commits only to 'endeavor to make every effort' to speed its own review, not to guarantee a fixed turnaround. Nothing in the chapter requires any builder to seek certification; it is an incentive layered on top of the standard South Fulton building permit process, not a substitute for it.

Violations & Fines

There is no fine or citation for skipping green building certification: this chapter creates a benefit, not a duty. A builder who does not submit certification proof simply gets no expedited review and proceeds through the standard plan review and permitting timeline that applies to every other project in the city.

Frequently Asked Questions

Does South Fulton require green building certification?
No. Chapter 13 is purely an incentive program. Builders may pursue LEED, EarthCraft House, or ENERGY STAR certification to earn expedited plan review, but nothing in the city code forces any project to meet a green building standard.
What do I have to submit to get expedited review?
Proof of registration in the LEED, EarthCraft House, or ENERGY STAR program, plus that program's checklist showing which credits you plan to pursue. Your intent must also appear on the building plans and the permit application under Sec. 14-13003(1).
Is expedited review guaranteed once I submit proof?
Not absolutely. Sec. 14-13004 acknowledges that projects requiring review by outside agencies can still extend the timeline; the city commits only to make every effort to expedite its own portion of the review.

Sources & Official References

Other rules in South Fulton

All South Fulton rules

Compare South Fulton to another location·View the Georgia building safety overview

Get notified when Green Building Code in South Fulton, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Green Building Code in Nearby Cities

How other cities in Fulton County handle green building code.

Atlanta, GA
Light Restrictions