Key Facts

Governing section
UDC § 4.4.6
Footing inspection
Before concrete is placed
Slab-prep inspection
After MEP rough-in backfilled
Foundation inspection
Before wall concrete/grout placed
Enforcing office
Alpharetta Building Inspection Division

Summary

The City of Alpharetta requires a fixed sequence of building inspections before construction can proceed: footing, slab-prep, and foundation inspections must each be requested and passed before concrete is poured, under the Unified Development Code.

4.Required Building Inspections. The Building Official, upon notification from the permittee, shall make the following building inspections and such other inspections as necessary to ascertain codes compliance ... a.FOOTING: To be made after trenches are excavated and cleaned; forms erected and supported; required reinforcing is properly secured in place and supported; and before any concrete is placed.b.SLAB-PREP: To be made after footings have been placed (if applicable); underground Mechanical, Electrical, and Plumbing (MEP) systems have been City inspected, approved, and properly backfilled ... and before any concrete is placed.c.FOUNDATION (When required): To be made after required wall reinforcement is in place and at least one side of concrete retaining wall forms are secured in place, wall cavities are cleaned, and second side forms are ready to be placed ... and before any concrete is placed.

Full Breakdown

Under Section 4.4.6 of the Unified Development Code, the Building Official inspects construction in the City of Alpharetta at defined stages, and none may be skipped. The FOOTING inspection happens after trenches are excavated and cleaned, forms are erected and supported, and required reinforcing steel is secured in place, all before any concrete is placed. The SLAB-PREP inspection follows, after footings are placed, underground mechanical, electrical, and plumbing systems have been City-inspected, approved, and backfilled, forms are erected, reinforcing is in place, rock base is set at below-grade slabs, and the vapor barrier is installed, again before concrete pours.

The FOUNDATION inspection covers concrete or masonry retaining walls and requires reinforcement and weep holes and piping sleeves in place with safe access provided for the inspector before concrete or grout is placed. Requests for these inspections go to the Building Inspection Division, and the building permit yard card must be posted and legible from the public street at all times; work cannot start until the card is posted, and lost or damaged cards must be replaced before further inspections proceed. If erosion control on the site is not being maintained per City Engineering Department requirements, inspectors will refuse to inspect at all and leave a Notice of Violation on the yard card until the permittee obtains a written release. Large or multi-floor buildings over 15,000 square feet may have mechanical and electrical wall/ceiling cover inspections performed in stages at the Building Official's discretion.

Violations & Fines

Continuing construction past a failed or unscheduled inspection stage triggers a Notice of Violation from the Building Official, and the permittee must correct the noted defect before any further inspection or continued work is allowed. No waiver letters, hold-harmless agreements, or contractor/engineer statements are accepted in place of a passed inspection. No Certificate of Occupancy will issue while any noted violation remains uncorrected, and the City Engineer, Building Official, or Director may issue an immediate stop-work order for work that is not authorized by the approved permit or plans.

Frequently Asked Questions

Can I pour concrete before the footing inspection in Alpharetta?
No. Section 4.4.6 requires the footing inspection to occur after trenches are excavated and reinforcing is secured, and specifically before any concrete is placed. Pouring early is a code violation that the Building Official can order corrected or halted with a stop-work order.
What triggers a stop-work order during inspections?
Work not authorized by the approved permit or plans, or that violates the Unified Development Code, subjects the site to an immediate stop-work order from the Director, Building Official, or City Engineer, per Section 4.4.6.D.
Why would an inspector refuse to inspect my Alpharetta site?
Section 4.4.6.C.2 bars any inspection when the site lacks an accessible permit yard card or effective erosion control measures required by the City Engineering Department; a written violation release is required first.

Sources & Official References

Other rules in Alpharetta

All Alpharetta rules

Compare Alpharetta to another location·View the Georgia building safety overview

Get notified when Building Inspections in Alpharetta, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Fulton County handle building inspections.

Atlanta, GA
Some Restrictions
Roswell, GA
Some Restrictions