Key Facts

Inspection stages
Foundation, frame, final
Enforcing office
Director, Bureau of Buildings
Reinspection fee
$50.00 per reinspection
Permit card
Must stay posted until C.O. issued

Summary

Atlanta requires three staged inspections on permitted construction: foundation, framing and final, each signed off by the Director before work continues.

The Director upon notification from the permit holder or agent, shall make the following inspections of buildings and such other inspections as may be necessary, and shall either approve that portion of the construction as completed or shall notify the permit holder or agent wherein the same fails to comply with the law: Foundation Inspection: To be made after trenches are excavated and forms erected.

Frame Inspection: To be made after the roof, all framing, fire-blocking and bracing is in place, all concealed wiring, all pipes, chimneys, ducts and vents are complete.

Final Inspection: To be made after the building is completed and ready for occupancy.

Full Breakdown

The Director of the Bureau of Buildings inspects permitted work at three fixed points: after trenches are excavated and forms erected (foundation), after the roof, framing, fire-blocking, bracing, concealed wiring, pipes, chimneys, ducts and vents are in place (frame), and once the building is complete and ready for occupancy (final). Work cannot proceed past any of these points without the Director's written approval, and the building permit card must stay posted on-site until a certificate of occupancy issues. A $50.00 reinspection fee applies after the initial inspection when corrections are required.

Violations & Fines

Continuing construction beyond a required inspection point without written Director approval is a code violation; covering reinforcing steel or structural framework before approval is separately prohibited, and a $50.00 fee applies to each reinspection needed after corrective work.

Frequently Asked Questions

What are Atlanta's required building inspections?
Foundation inspection after trenches and forms are in, frame inspection once framing and rough-in work are complete, and a final inspection before occupancy.
Can I keep building before an inspection is approved?
No. Work cannot go past the point covered by each inspection until the Director gives written approval, and covering structural framework early is also prohibited.

Sources & Official References

Other rules in Atlanta

All Atlanta rules

Compare Atlanta to another location·View the Georgia building safety overview

Get notified when Building Inspections in Atlanta, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Fulton County handle building inspections.

Roswell, GA
Some Restrictions