Atlanta, GA Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

EVSE Capable spaces required
20% of required parking spaces
EVSE Installed (Level-2) spaces required
Another 20% of required parking
Applies to
All new multi-family, mixed-use, S-2 garages
City-owned new lots
50% capable, 25% installed
Minimum charger rating
Level-2, at least 9,600 VA

Summary

New multi-family, mixed-use, and parking-garage construction in Atlanta must wire at least 20% of required parking spaces for future EV chargers and install working Level 2 chargers at another 20%, under the Electrical Code amendments.

All new occupancy classifications, including all new construction for mixed use zoning classifications and all new S-2 parking garages, including S-2 parking garages associated with other new occupancies classifications, shall meet the requirements for EVSE Capable and EVSE Installed established in this Section, to accommodate the installation of EVSE and Charging Stations. ... EVSE Capable parking spaces shall comprise 20% (or 1:5) of the required parking spaces. EVSE Installed parking spaces shall comprise 20% (or 1:5) of the required parking spaces in addition to EVSE Capable Spaces.

Full Breakdown

Section 101.8 of the Electrical Code Amendments (Appendix B) requires every new occupancy classification -- including new multi-family and mixed-use residential buildings and any new S-2 parking garage -- to provide EVSE Capable and EVSE Installed parking spaces. EVSE Capable spaces (wired raceway only) must equal 20% of required parking; EVSE Installed spaces, each with a working Level-2 charger rated at least 9,600 VA, must equal another 20%. New off-street parking built or expanded by the City itself faces higher ratios: 50% EVSE Capable and 25% EVSE Installed. The Office of Buildings enforces the standard through electrical permit review.

Violations & Fines

Projects that skip the required EVSE wiring or chargers fail final electrical inspection with the Office of Buildings, which can withhold permit sign-off and the certificate of occupancy until compliance is corrected.

Frequently Asked Questions

Does this apply to new apartment buildings in Atlanta?
Yes. Section 101.8 covers all new occupancy classifications, which includes new multi-family and mixed-use residential construction and any new S-2 parking garage built to serve it.
What's the difference between EVSE Capable and EVSE Installed?
EVSE Capable spaces get only the wiring and raceway for a future charger. EVSE Installed spaces must already have a working Level-2 charger rated at least 9,600 VA.
Does this apply to existing apartment buildings?
No -- Section 101.8 applies to new construction, new S-2 parking garages, and expansions of existing parking footprints; it does not retrofit older buildings that aren't adding parking.

Sources & Official References

Other rules in Atlanta

All Atlanta rules

Compare Atlanta to another location·View the Georgia parking rules overview

Get notified when EV Charging in Atlanta, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.