Key Facts

Governing rule
CBC Sec. 109.10 as added locally
Fee trigger
incomplete work or uncorrected items
Other triggers
missing record card, blocked site access
Request method
written application on city form
Consequence of nonpayment
no further inspections performed
First failed inspection
no fee, per the code's own text

Summary

Camarillo can charge a reinspection fee whenever a building inspection finds the work incomplete or the required corrections unmade, and the city will not schedule further inspections until that fee is paid.

109.10 Reinspection Fees. A reinspection fee may be imposed for each inspection or reinspection, when such portion of work for which inspection is called is not complete or when required corrections are not made.

This section is not to be interpreted as requiring reinspection fees the first time a job is rejected for failure to comply with the requirements of the technical codes, but as a method of controlling the practice of calling inspections before the job is ready for such inspection or reinspection.

Reinspection fees may be imposed when the inspection record card is not posted, or otherwise not available on the work site; the approved plans are not readily available to the inspector; for failure to provide access on the date for which the inspection is requested; or for deviating from plans requiring the approval of the Building Official.

To obtain a reinspection, the applicant must file an application in writing upon a city-approved form and pay the applicable reinspection fee.

In instances where reinspection fees have been assessed, additional inspection of the work will not be performed until the required fees have been paid.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 27 Update 1).

Full Breakdown

Camarillo Municipal Code Sec. 10 to the California Building Code and governs what happens when a scheduled building inspection does not pass. A reinspection fee may be imposed for each inspection or reinspection called when the portion of work being inspected is not complete or the corrections the inspector previously required have not been made. The code is explicit that this is not meant to punish a contractor the first time a job fails inspection for not meeting the technical codes; instead it targets the practice of repeatedly calling for inspections before the work is actually ready.

The ordinance lists specific triggers beyond a failed correction: a reinspection fee can also be charged when the inspection record card is not posted or available on site, when approved plans are not readily available to the inspector, when the site cannot be accessed on the date requested, or when the built work deviates from plans in a way that needed the Building Official's approval first. To actually get a reinspection, the applicant must file a written application on a city-approved form and pay the applicable fee up front.

Once a reinspection fee has been assessed, Camarillo will not perform any additional inspection of the work until the outstanding fee is paid in full, which effectively halts progress on the project at that inspection stage. 04 permit and inspection framework, which also sets a 12-month permit expiration under Sec. 035 and a 180-day abandonment period for suspended work, so a stalled reinspection can interact with those other deadlines if it drags on.

Violations & Fines

Unpaid reinspection fees stop work at the inspection stage: the code states that no additional inspection will be performed until required fees are paid, which can delay occupancy or close-out of the permit. Because the permit itself remains subject to Sec. 16.04.035's 12-month validity and 180-day suspension limits, an unresolved reinspection dispute risks the underlying permit expiring, requiring a new permit application and a new full permit fee to restart the work.

Frequently Asked Questions

Does Camarillo charge for every failed building inspection?
Not automatically the first time. Sec. 16.04.055 says the reinspection fee is not meant to apply the first time a job is rejected for failing to meet the technical codes; it targets repeated inspections called before work is actually ready.
What else can trigger a reinspection fee besides unfinished work?
The inspection record card not being posted or available, approved plans not being available to the inspector, no site access on the requested date, or built work deviating from plans requiring the Building Official's approval can all trigger a reinspection fee under Sec. 16.04.055.
Can work continue if I do not pay a reinspection fee?
No. Once a reinspection fee is assessed, Camarillo will not perform any additional inspection of the work until the required fee is paid, which stops the project from moving past that inspection stage.
How do I request a reinspection in Camarillo?
The applicant must file a written application on a city-approved form and pay the applicable reinspection fee before the Building Official will schedule the reinspection, per Sec. 16.04.055.

Sources & Official References

Other rules in Camarillo

All Camarillo rules

California rules heatmap·Compare Camarillo to another location·View the California building safety overview

Get notified when Building Inspections in Camarillo, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Ventura County handle building inspections.

Ventura, CA
Some Restrictions
Simi Valley, CA
Some Restrictions
Oxnard, CA
Some Restrictions