Camarillo, CA Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
CMC Sec. 16.04.265
Permit application expires
180 days unless pursued/extended
Issued permit expires
If work not started within 12 months
Work without a permit
Investigation fee equals full permit fee
Fee refund cap
80% if no work performed
Penalty
Misdemeanor, up to $1,000 / 6 months

Summary

Electrical work in Camarillo is permitted under the same Chapter 1, Division II building-code administrative rules as every other trade: Sec. 16.04.265 applies them to the California Electrical Code, with a 180-day application deadline, a 12-month start deadline, and misdemeanor penalties under Sec. 16.04.310.

16.04.265 - California Electrical Code Administration provisions. The administrative provisions of the California Building Code contained in Chapter 1, Division II, of that code and as modified in of the Camarillo Municipal Code, are used for the administrative provisions governing the California Electrical Code, including violation and penalty provisions, which are governed by Camarillo Municipal Code ... Se ... c. 16.04.310.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 27 Update 1).

Full Breakdown

Municipal Code Sec. 265, adopted by Ord. No. 2034, Sec. 2 (11-12-2025), provides that the administrative provisions of Chapter 1, Division II of the California Building Code, as modified locally, govern permitting, inspection and enforcement of work regulated by the California Electrical Code, and that violations and penalties are handled under Sec. 310. Those shared rules set concrete deadlines for electrical permit holders: Sec. 030 (CBC Sec. 2) deems an application abandoned 180 days after filing unless pursued in good faith, with extensions of up to 180 days each available for justifiable cause.

Sec. 035 (CBC Sec. 5) voids an issued electrical permit if work hasn't started within 12 months of issuance or is suspended for 180 days; reviving it within a year costs half the original fee, while a lapse beyond a year requires a new permit at full fee. Sec. 045 (CBC Sec. 8) charges an investigation fee equal to the permit fee whenever electrical work is found to have been started without a permit. Sec. 050 (CBC Sec. 9) limits refunds to 80 percent of the permit or plan-review fee, requested in writing within 180 days of payment, and Sec. 055 (CBC Sec. 10) authorizes reinspection fees for work called in before it is ready or when plans aren't available on site.

Violations & Fines

Performing, or permitting, electrical work in violation of the adopted Electrical Code or these administrative provisions is a misdemeanor under Sec. 16.04.310, carrying a fine of up to $1,000, up to six months in jail, or both, with each day of continued violation treated as a separate offense. The Code Compliance Division created by Sec. 16.04.316 enforces the chapter, and the city council serves as the board of appeals under Sec. 16.04.020.

Frequently Asked Questions

Do I need a city permit for electrical work in Camarillo?
Yes. Sec. 16.04.265 applies the city's building-permit administrative process to all work regulated by the California Electrical Code, so wiring and panel work require the same permit and inspection steps as other construction.
How long do I have before a Camarillo electrical permit application expires?
The application is deemed abandoned 180 days after filing unless pursued in good faith, though the Building Official can grant written extensions of up to 180 days at a time for justifiable cause, under Sec. 16.04.030.
What if an electrician starts work before the permit is issued?
Sec. 16.04.045 requires a special investigation and an investigation fee equal to the full permit fee, charged in addition to the permit fee, and it does not excuse the contractor from any other code requirement or penalty.
Can I recover fees if I cancel my electrical permit application?
Sec. 16.04.050 lets the Building Official refund up to 80 percent of the plan-review or permit fee if no work was performed, but only on a written request filed within 180 days of the original payment.

Sources & Official References

Other rules in Camarillo

All Camarillo rules

California rules heatmap·Compare Camarillo to another location·View the California building safety overview

Get notified when Electrical Permits in Camarillo, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Ventura County handle electrical permits.

Ventura, CA
Some Restrictions
Moorpark, CA
Some Restrictions
Thousand Oaks, CA
Some Restrictions
Simi Valley, CA
Some Restrictions
Oxnard, CA
Some Restrictions