Long Beach, CA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Notice before inspection
at least 1 working day, § 18.07.030(A)
First required inspection
footing and foundation
Last required inspection
final inspection, before occupancy
Approval required
written sign-off before covering work, § 18.07.040
Special inspectors
required for listed CBC Ch. 17 work, § 18.07.080
Concealed-work order
exposure at no cost to City, § 18.03.020(G)

Summary

Every permitted building project in Long Beach runs through a fixed inspection sequence under LBMC § 18.07.050, footing and foundation, framing, energy efficiency and a final inspection before occupancy, each one requiring the Building Official's written approval before work can proceed to the next stage.

A. Building. The Building Official, upon notification as specified in Section 18.07.030, shall make the inspections set forth in subsection, if applicable. 1. Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place. For concrete foundations, any required forms shall be in place prior to inspection. [...] 15. Final inspection. Final inspection shall be made after all work required by the permit is completed and prior to occupancy.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 52 Update 1 | City Charter: Supplement 5).

Full Breakdown

Long Beach Municipal Code § 18.07.050(A) lists the staged inspections the Building Official must make on any permitted building project, each triggered by written notification from the permit holder under § 18.07.030(A), which requires at least one working day's notice. The sequence starts with the footing and foundation inspection, made after footing excavations are complete and reinforcing steel is placed, followed in turn by the concrete slab and under-floor inspection, a methane gas mitigation system inspection where applicable, a lowest-floor-elevation check in flood hazard areas, the frame inspection once roof deck, framing, fire blocking, bracing and rough utilities are in and approved, and inspections for lath/gypsum board, fire- and smoke-resistant penetrations, and energy efficiency compliance with the California Energy Code adopted in Chapter 18.46.

Work may not proceed past any of these stages without the Building Official's written approval under § 18.07.040: nothing that is inspected may be covered or concealed until it is signed off. Certain work additionally requires a registered special inspector under § 18.07.080 for the categories listed in Chapter 17 of the California Building Code. The sequence ends with the final inspection, made after all permitted work is complete and before occupancy, and required before the Building Official issues a Certificate of Occupancy under § 18.08.010. Parallel inspection sequences apply to electrical, plumbing, mechanical and grading work under § 18.07.050(B) through (E).

Violations & Fines

Covering or concealing work before the required inspection is a Code violation under § 1.32.010: a misdemeanor with up to $1,000 and six months in jail, or an infraction, each day a separate offense. The Building Official can order exposure of concealed work under § 18.03.020(G) at the responsible party's expense, and stop further work under § 18.03.020(H).

Frequently Asked Questions

What inspections does a Long Beach building permit require?
Under LBMC § 18.07.050(A), a building permit triggers a staged sequence: footing and foundation, concrete slab/under-floor, framing, lath and gypsum board, energy efficiency, and a final inspection before occupancy, plus specialty checks like methane mitigation and flood-elevation certification where they apply.
How much notice do I need to give before an inspection?
At least one working day. LBMC § 18.07.030(A) makes it the permit holder's duty to notify the Building Official when work is ready and to provide access for the inspection, which can be requested in writing, by phone, or another method the Building Official accepts.
Can I cover up work before it's inspected?
No. Section 18.07.040 bars doing any further work past an inspection point without the Building Official's written approval, and § 18.03.020(G) lets the City order concealed work exposed for inspection at no cost to the City if it was covered without being checked first.
What's the last inspection before I can occupy a new building?
The final inspection under § 18.07.050(A)(15), made after all permitted work is complete. It has to happen before the Building Official issues a Certificate of Occupancy under § 18.08.010, and in flood hazard areas it also requires submitting flood-elevation documentation first.

Sources & Official References

Other rules in Long Beach

All Long Beach rules

California rules heatmap·Compare Long Beach to another location·View the California building safety overview

Get notified when Building Inspections in Long Beach, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Los Angeles County handle building inspections.

Carson, CA
Some Restrictions
Downey, CA
Some Restrictions
Lakewood, CA
Some Restrictions
Lancaster, CA
Some Restrictions
Los Angeles, CA
Some Restrictions
Norwalk, CA
Some Restrictions
Palmdale, CA
Some Restrictions
Pasadena, CA
Some Restrictions