Los Angeles, CA Building Safety: Building Inspections (2026)
Key Facts
- Governing section
- LAMC § 91.108.5
- Number of required inspections
- Seven, foundation through final
- Notice required
- One working day before inspection
- Cover-up rule
- No concealment before approval, § 91.108.4
- Inspection record
- Posted card issued with permit
Summary
Los Angeles requires permit holders to call for inspection at seven defined construction stages, from foundation excavation through final sign-off. LAMC § 91.108.5 lists each required inspection, and § 91.108.4 bars covering any completed work until the Superintendent of Building approves it.
It shall be the duty of the person doing the work authorized by a permit to notify the Superintendent of Building that such work is ready for inspection... Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the Superintendent of Building. ... Any portions which do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the Superintendent.
Full Breakdown
3 puts the burden on the person doing the permitted work: "It shall be the duty of the person doing the work authorized by a permit to notify the Superintendent of Building that such work is ready for inspection," and the Superintendent may require that request at least one working day in advance, by phone or in writing. 5 then lists the seven inspections every project must call for as it proceeds: foundations, once footing forms and reinforcing steel are placed but before concrete is poured; wood framing and ventilation equipment, once framing, fire stopping and rough pipes/ducts are in but before covering; wall covering, once lath or drywall backing is ready for plaster or taping; reinforced concrete and reinforced masonry, at their respective reinforcing-steel stages; structural steel, once members and connections are in place but before concealment; and a final inspection once the structure is complete and ready for occupancy. 6 to verify compliance with any other code it enforces.
Violations & Fines
Covering framing, wiring, plumbing or reinforcing steel before the Department has approved that stage violates § 91.108.4, and the Department can require the work to be uncovered and re-exposed for inspection at the owner's expense. Proceeding past a required inspection point without approval can also trigger a stop-work order and delay issuance of the final Certificate of Occupancy.
Frequently Asked Questions
What inspections does a Los Angeles building permit require?
Can I cover framing before the inspector signs off in LA?
How much advance notice does LA require for an inspection request?
Sources & Official References
Other rules in Los Angeles
California rules heatmap·Compare Los Angeles to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in Los Angeles County handle building inspections.