Key Facts

Inspecting officer
Code Official, Community Development Department
Footing inspection
After excavation is complete and reinforcing is in place
Rough-in
Approved before any work is concealed
Final inspection
After all permitted work is complete and ready for occupancy
Heating equipment replacement
Inspection request within 48 hours of completion
Fine on conviction
Not to exceed $500.00

Summary

Work under a Paola building permit is inspected by the Code Official at set stages: footing or foundation, underground, slab, waterproofing, rough-in, roofing, siding, gas piping, lath and gypsum board, fire-resistant penetrations, attic insulation and final. Work must stay exposed until approved, and the permit holder must request each inspection.

(a) General. ... Construction or work for which a permit is required shall be subject to inspection by the Code Official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... (c) Required Inspections. The Code Official, upon notification, shall make the inspections set forth herein. (1) Footing or foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel and chairs are in place. ... (6) Rough-in inspection. Rough-in inspection shall be approved prior to any work requiring inspection being concealed. ... (16) Final inspection. The final inspection shall be made after all work required by the building permit is completed and the structure is ready for occupancy. ... (f) Inspection Requests. It shall be the duty of the holder of the building permit or their duly authorized agent to notify the Code Official when work is ready for inspection.

Full Breakdown

Section 4-109(a) of the Paola City Code makes any construction or work that needs a permit subject to inspection by the Code Official and requires it to remain accessible and exposed until approved. Keeping it exposed is the duty of the permit applicant, and neither the Code Official nor the City is liable for the expense of removing or replacing material to allow inspection.

Section 4-109(c) lists the required stages. The footing or foundation inspection comes after excavations for footings are complete and any required reinforcing steel and chairs are in place, with forms in place for concrete foundations. The underground inspection comes after trenches are excavated and bedded and service piping or conduit is in place but before backfill. The slab or under-floor inspection comes before any concrete is placed or floor sheathing installed. Drain tile and foundation waterproofing are inspected before backfill, with drain tile bedded in clean rock and drain ends exposed. In flood hazard areas, a Kansas licensed land surveyor or registered engineer must provide an elevation certificate for the lowest floor before further vertical construction. Rough-in must be approved before any work requiring inspection is concealed, and it covers the frame, building envelope, fireblocking, firestopping and the concealed electrical, plumbing, mechanical, gas and fire protection piping.

The list continues with an HVAC duct liner spot check, the roof covering inspection before the final roof covering, the vapor barrier and siding inspection during siding application, gas piping rough-in with a pressure test, lath and gypsum board before plastering or taping, fire-resistant penetrations that stay uncovered until approved, and attic access for insulation at final inspection. The final inspection comes after all permitted work is complete and the structure is ready for occupancy. The 2018 building code amendment at § 4-201(a)(3)(T) adds roofing inspections at the midpoint of roofing installation and after it is complete.

The permit holder or authorized agent must notify the Code Official when work is ready (§ 4-109(f)), furnish the equipment, material and labor for tests (§ 4-109(e)), and keep working only within the last approval (§ 4-109(g)). Replacement heating equipment can run if an inspection request is filed within forty-eight hours of completing the replacement.

Violations & Fines

Work cannot go beyond an inspection point without the approval of the Code Official, and any failing portion must be corrected and left uncovered until authorized (§ 4-109(g)). Covering work before approval leaves the permit applicant to pay for opening it up (§ 4-109(a)). Under § 4-111(d), erosion control measures that are not in place and maintained fail the inspection and future inspections are denied. A person convicted of violating Chapter 4 faces a fine not to exceed $500.00 (§ 4-113(b)).

Frequently Asked Questions

Who requests an inspection in Paola?
The holder of the building permit or their authorized agent. Section 4-109(f) makes it their duty to notify the Code Official when work is ready for inspection and to provide access and a means for inspection. The Code Official, upon notification, then makes the inspections the section requires.
What happens if I cover the work before it is inspected?
Work cannot be done beyond the point of an inspection without approval, and failing portions must not be covered or concealed until the Code Official authorizes it. Because the work must remain accessible and exposed until approved, the applicant, not the City, pays to remove and replace material so the inspector can see it.
Is anything inspected after the final inspection?
The final inspection under § 4-109(c)(16) happens once all permitted work is done and the structure is ready for occupancy. Then § 4-110 bars use or occupancy until the Code Official issues a certificate of occupancy. A temporary certificate lasts a maximum of thirty days for commercial structures and sixty days for residential.
Can a private inspector replace the City inspection?
Only with permission. The Code Official can accept reports of approved inspection agencies that meet qualification and reliability requirements, but a written request must be submitted and an authorization received before the outside agency performs any inspection (§ 4-109(d)). Reports must be in writing and certified (§ 4-104(d)).

Sources & Official References

Other rules in Paola

All Paola rules

Compare Paola to another location·View the Kansas building safety overview

Get notified when Building Inspections in Paola, KS changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.