Paola, KS Building Safety: Plumbing Permits (2026)
Key Facts
- Permit authority
- Code Official, Community Development Department
- Adopted code
- 2018 International Plumbing Code, dated January, 2018
- Exterior water supply piping depth
- Not less than 36 inches below grade
- Building sewer depth
- Minimum of 12 inches below grade
- Plumbing contractor license fee
- $150.00 (Table 4-411)
- Fine on conviction
- Not to exceed $500.00
Summary
In Paola, an owner or authorized agent who installs, alters, repairs, removes, converts or replaces a plumbing system regulated by the building code must first apply to the Code Official for a permit. Section 4-203 adopts the 2018 International Plumbing Code with local amendments, including 36-inch water pipe depth.
(F) 105.1 Required. Any owner or authorized agent who intends to ... or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be done shall first make application to the Code Official and obtain the required permit. ... PLUMBING: (1) The stopping of leaks in drains, water, soil, waste or vent pipe; provided however, that if any concealed trap, drain pipe, water, soil, waste or vent pipe becomes defective and it becomes necessary to remove and replace the same with new material, such work shall be considered as new work and a permit shall be obtained and inspection made as provided in this code. ... (a) There is incorporated by reference, for the purpose of adopting regulations, provisions, terms and specifications for the control of buildings and structures within the City of Paola, the 2018 International ... Plumbing Code, dated January, 2018, as published by the International Code Council, Inc., excepting only such parts or portions thereof as are specifically deleted or amended by this Section
Full Breakdown
Section 4-105(a) of the Paola City Code requires an owner or authorized agent to apply to the Code Official and obtain the permit before erecting, installing, enlarging, altering, repairing, removing, converting or replacing a plumbing system whose installation the code regulates. A contractor who regularly employs one or more qualified trade persons can hold an annual permit instead, covering alterations to an already approved plumbing installation. The exemptions in § 4-105(b)(5) are narrow. Stopping leaks in drains, water, soil, waste or vent pipe needs no permit, but if a concealed trap or pipe is defective and has to be removed and replaced with new material, that is new work and needs a permit and inspection. Clearing stoppages, repairing leaks in pipes, valves or fixtures and removing and reinstalling water closets also need no permit, provided the repair does not involve replacing or rearranging valves, pipes or fixtures. The building code amendment at § 4-201(a)(3)(F) repeats the permit rule and adds that an original letter of intent from all contractors listed on the permit, stating that they will perform work on the project, must be submitted before a building permit issues.
Section 4-203(a) incorporates the 2018 International Plumbing Code, dated January, 2018, as published by the International Code Council. A copy is marked "Official Copy as Adopted by Ordinance No. 3005" and filed with the City Clerk. The local amendments in § 4-203(a)(2) retitle the code the City of Paola Plumbing Code and set depths: exterior water supply piping must be installed not less than thirty-six inches below grade, and building sewers must be a minimum of twelve inches below grade. They also require oil separators at repair garages, gasoline stations with grease racks, grease pits or work racks, car washing facilities with engine or undercarriage cleaning capability, and factories producing oily and flammable liquid wastes. Cross-connections are prohibited except where approved protective devices are installed, and double check valves cannot serve any required cross-connection control application.
Inspections follow the permit. The underground inspection covers water supply and wastewater piping before backfill, and the rough-in inspection covers plumbing that will be concealed (§ 4-109(c)(2), (6)). The plumber must hold a Paola contractor license: § 4-405 bars a building permit for an unlicensed contractor, and § 4-410(c) requires a master plumbing with gas certificate of competency with the application. Table 4-411 lists the plumbing contractor license fee as $150.00.
Violations & Fines
Starting plumbing work without the permit draws double the normal permit fee under the amended building code section 109.4, and § 4-301(d) adds an investigation fee equal to the permit fee. It is unlawful to perform work as a contractor without a license (§ 4-405), and no permits are issued to a contractor without a current license (§ 4-413(c)(2)). A person convicted of violating Chapter 4 faces a fine not to exceed $500.00 (§ 4-113).
Frequently Asked Questions
Do I need a permit to fix a leaking pipe in Paola?
Which plumbing code does Paola use?
How deep must water and sewer lines be buried in Paola?
Can I do my own plumbing at my house?
Sources & Official References
Other rules in Paola
Compare Paola to another location·View the Kansas building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.