Tamarac, FL Building Safety: Building Inspections (2026)
Key Facts
- Trigger age
- 25 years old, then every 10 years
- Covered buildings
- Condo/co-op, 3+ habitable stories
- Phase 1 deadline
- 180 days after notice
- Repair start deadline
- 365 days after phase 2 report
- Registration deadline
- 180 days after notice
- Daily fine
- Up to $1,000 per violation per day
Summary
In the City of Tamarac, condominium and cooperative buildings three or more habitable stories tall must pass a mandatory milestone inspection once they reach 25 years old, repeating every 10 years. City Code Sec. 5-79 runs the two-phase process and the building official's office administers registration, fees and enforcement locally.
(a)Applicability. The Broward County Board of Rules and Appeals requires structural and electrical safety inspections for buildings twenty-five (25) years old or older and every ten (10) years after the actual year built. This section applies to condominium and cooperative buildings that are three (3) or more habitable stories in height, consistent with F.S. § 553.899. ... 3.Milestone inspection. A milestone inspection consists of two (2) phases and shall be in accordance with F.S. § 553.899. ... The phase one milestone report must be performed within one hundred eighty (180) days after the property owner's receipt of the city's notice of required inspection. If a phase one report inspection indicates substantial structural deterioration, a phase two milestone inspection must be performed. ... 4.Failure to comply with the timelines established in this section may result a fine of up to one thousand dollars ($1,000.00) per violation per day against the property owner pursuant to the City Code.
Full Breakdown
City Code Sec. 5-79 applies the Broward County Board of Rules and Appeals' structural and electrical safety inspection requirement to condominium and cooperative buildings in Tamarac that are three or more habitable stories high, at the 25-year mark and every 10 years after, consistent with F.S. § 553.899. Single-family through four-family homes of three or fewer stories, government buildings, schools under the Broward County School Board, buildings under 3,500 square feet and most townhouses are exempt. The milestone inspection consists of two phases. In phase one, the responsible engineer or architect must complete the report within 180 days of the property owner's receipt of the city's notice of required inspection, and must tell the building official in writing whether the building may continue to be safely occupied; if the phase one report shows substantial structural deterioration, a phase two inspection follows with its own occupancy-opinion letter.
Reports go in digitally through the City of Tamarac online permitting system unless the owner cannot submit electronically. Based on the phase two report, required repairs must start within 365 days of the association receiving it, and the building permit application must cite the phase two report directly; all repairs are inspected through the city's own permitting process. Condo and co-op associations covered by the program must self-register through the city's online system within 180 days of being notified, and any new qualifying association must register before its certificate of occupancy is issued.
The city reports building counts, inspection status, permits issued and unsafe-structure determinations to the Department of Business and Professional Regulation by December 31 each year starting 2025.
Violations & Fines
Failing to meet the Sec. 5-79 timelines exposes the property owner to a fine of up to $1,000 per violation, per day, under the City Code, with each day of noncompliance a separate offense. The city can also pursue injunctive relief and civil penalties through the courts, and every remedy in the section is cumulative rather than exclusive, so the city may combine daily fines with a court action against the same association. Extensions follow F.S. § 553.899, and administrative fees are set by Tamarac's adopted fee schedule.
Frequently Asked Questions
Which Tamarac buildings need a milestone inspection?
What happens if a Tamarac condo misses the inspection deadline?
How do the two inspection phases work?
Sources & Official References
Other rules in Tamarac
Florida rules heatmap·Compare Tamarac to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in Broward County handle building inspections.