Tamarac, FL Building Safety: Building Permits (2026)
Key Facts
- Governing sections
- Tamarac Code §§ 5-26, 5-28
- Building code
- Florida Building Code, as amended, adopted by reference
- Pre-construction survey
- surveyor's certificate and site plan required
- Post-foundation check
- as-built survey confirms setback compliance
- Fee escalation
- adjusts each Oct. 1 by 3% or CPI
- Defect insurance
- $1,500 minimum bond/insurance per new unit
Summary
Tamarac Code § 5-26 adopts the Florida Building Code, as amended, to govern all construction, maintenance, repair, and condemnation of buildings in the city. Section 5-28 requires a surveyor's certificate and site plan with new construction and additions, and a post-foundation survey verifying setback compliance before construction may continue.
Pursuant to chapter 2000-141, Laws of Florida, the Florida Building Code, as amended, in book form, is adopted by reference as the building code of the city, and its regulations shall govern the construction, maintenance, repair and condemnation of buildings in the city. ... (a)Application for permit for new construction and additions, alterations and/or repairs, shall be accompanied by a registered land surveyor's certificate and plan in duplicate on which shall be clearly indicated the property corner stakes, property lines, dimensions, any existing structures and their location, existing rights-of-way, sidewalks and easements. ... The building official may waive the requirements for such survey when property line stakes are existing and known to be in place, and the work involved is minor and/or is clearly within the building setback lines.
Full Breakdown
Section 5-26, adopted under chapter 2000-141, Laws of Florida, and last amended in 2003, makes the Florida Building Code, as amended, the city's building code, automatically incorporating every state and local amendment as it is adopted, so builders and permit applicants must track the current statewide edition rather than a frozen local text. Permit fees are set by resolution of the city commission and automatically escalate each October 1 by the greater of 3 percent or the June Consumer Price Index, under § 5-1, with a two-year staff review of labor and material costs; plan-processing fees are non-refundable, but other permit fees can be refunded within 30 days of issuance or credited toward another permit within 90 days after a cancelled permit under § 5-1(c).
Before the city will issue a permit for new construction or an addition, alteration, or repair under § 5-28(a), the applicant must submit a registered land surveyor's certificate and duplicate site plan showing property corner stakes, lot lines, dimensions, existing structures, rights-of-way, sidewalks, and easements, plus the first-floor elevation relative to mean sea level for new construction; the building official can waive the survey only for minor work clearly within the setback lines where property stakes already exist. After the foundation or slab is poured, § 5-28(b) requires a second surveyor's certification of the as-built foundation location and elevation, confirming all setbacks are met, before construction can continue.
Certificates of occupancy carry their own separate fee schedule on file with the city clerk under § 5-27, and § 5-29 additionally requires new-home builders to post insurance or a bond of at least $1,500.00 per unit to cover post-occupancy construction defects before a certificate of occupancy issues, unless the buyer already has state-approved warranty insurance or the home is owner-built for personal, two-year occupancy.
Violations & Fines
Starting construction, an addition, alteration, or repair without first obtaining a building permit under § 5-28, or continuing construction after a permit has expired, makes the resulting structure presumptively unsafe under § 5-29's unsafe-building standard and can require it to be brought back into compliance. Skipping the required pre-slab surveyor's certificate or the post-foundation as-built survey under § 5-28 violates that section directly. General Code violations are punished under the citywide general penalty in § 1-13: up to $500.00, up to 90 days in jail, or both.
Frequently Asked Questions
What do I need to submit for a Tamarac building permit?
Do I need another survey after the foundation is poured in Tamarac?
Which building code does Tamarac use?
Sources & Official References
Other rules in Tamarac
Florida rules heatmap·Compare Tamarac to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in Broward County handle building permits.