Skip to main content
CityRuleLookup

Shoreline, WA Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
Uniform Plumbing Code under SMC § 15.05.010(F)
Excluded from adoption
Sewer and fuel gas piping provisions
Adopted appendices
A, B, D, I and M only
Fee refund
Up to 80% if unstarted, within 180 days
Enforcement
Civil infraction or misdemeanor up to $1,000

Summary

Shoreline adopts the Uniform Plumbing Code, published by the International Association of Plumbing and Mechanical Officials, as its plumbing code under SMC § 15.05.010(F), but carves out sewer and fuel gas piping provisions and adopts only five specific technical appendices, so plumbing permits and inspections in the city follow the UPC rather than the International Plumbing Code.

F. Except as provided in RCW 19.27.170, the current edition of the Uniform Plumbing Code and Uniform Plumbing Code Standards, published by the International Association of Plumbing and Mechanical Officials, as adopted by the Washington State Building Code Council in Chapters 51-56 and 51-57 WAC, as now or hereafter amended; provided, that any provisions of such code affecting sewers or fuel gas piping are not adopted. The following appendices are specifically adopted: 1. Appendix A, Recommended Rules for Sizing the Water Supply System; 2. Appendix B, Explanatory Notes on Combination Waste and Vent Systems; 3. Appendix D, Sizing Storm Water Drainage Systems; 4. Appendix I, Installation Standards; 5. Appendix M, Peak Water Demand Calculator, as adopted in WAC 51-56-003.

Full Breakdown

SMC § 15.05.010(F) makes the Uniform Plumbing Code (UPC) and its companion Uniform Plumbing Code Standards, as adopted by the Washington State Building Code Council in Chapters 51-56 and 51-57 WAC, the plumbing code that governs every water supply, drain, waste and vent installation inside the City of Shoreline. The city's amendment excludes any UPC provision covering sewers or fuel gas piping, which fall instead under the surface water and fuel gas chapters the city separately adopts, and it limits which UPC appendices apply: only Appendix A (sizing the water supply system), Appendix B (combination waste and vent systems), Appendix D (sizing storm water drainage systems), Appendix I (installation standards), and Appendix M (the peak water demand calculator adopted through WAC 51-56-003) carry the force of law.

Because a Peak Water Demand Calculator appendix is specifically adopted, plumbers sizing a water service for a new single-family home or a multifamily building must use that calculator rather than an older fixture-unit table when the WAC 51-56-003 provision applies. Every plumbing permit fee runs through the general fee schedule adopted under Chapter 3.01 SMC and administered by SMC § 15.05.020(A), which lets the city manager or designee refund up to 80 percent of a paid fee when no work has started, or the full fee if it was paid in error, on a written request filed within 180 days of payment.

SMC § 15.05.020(B) directs that any UPC reference to a 'code official' means the city manager or designee, so plumbing inspections and permit decisions run through the same Planning and Community Development staff who administer the building and mechanical codes.

Violations & Fines

Plumbing work performed without a permit, or installed contrary to the adopted Uniform Plumbing Code appendices, is a code violation enforceable under SMC § 20.30.770: the city may issue a Class 1 civil infraction under Chapter 7.80 RCW, or pursue a misdemeanor charge carrying up to a $1,000 fine and 90 days in jail for willful violations, with each week of continued work a separate offense.

Frequently Asked Questions

What plumbing code applies in Shoreline?
The Uniform Plumbing Code, published by the International Association of Plumbing and Mechanical Officials, applies under SMC § 15.05.010(F), as adopted by the Washington State Building Code Council. Shoreline excludes the UPC's sewer and fuel gas piping sections, which are governed elsewhere in the municipal code.
Which UPC appendices does Shoreline enforce?
Only five: Appendix A on sizing the water supply system, Appendix B on combination waste and vent systems, Appendix D on sizing storm water drainage systems, Appendix I on installation standards, and Appendix M, the peak water demand calculator adopted through WAC 51-56-003.
Can I get part of my plumbing permit fee back if I cancel?
Yes. SMC § 15.05.020(A) allows the city manager or designee to refund up to 80 percent of a permit fee when no work has been done, provided you file a written request within 180 days of the date you paid.

Sources & Official References

Other rules in Shoreline

All Shoreline rules

Compare Shoreline to another location·View the Washington building safety overview

Get notified when Plumbing Permits in Shoreline, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Nearby Cities

How other cities in King County handle plumbing permits.

Renton, WA
Some Restrictions
Kirkland, WA
Some Restrictions
Kent, WA
Some Restrictions
Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions
Federal Way, WA
Some Restrictions
Seattle, WA
Some Restrictions