Key Facts

Final inspection
Signed permit card = certificate of occupancy
Governing rule
IRC § R110.3, SMC § 15.05.040
Work must stay
Accessible/exposed until approved
Demolition permit validity
60 days, one 60-day extension
Inspecting official
City manager or designee (building official)

Summary

In the City of Shoreline, a building permit is not finished until a final inspection is signed off: SMC § 15.05.040 amends the International Residential Code's Section R110.3 so that a dated, authorized signature entered on the permit card under the 'Final' inspection line is itself the certificate of occupancy the code requires. Work stays open to inspection at every stage until the building official closes it out.

R110.3 Certificate issued. An issued permit card affixed with a dated, authorized signature entered under the “Final” inspection shall constitute the certificate of occupancy required by this code.

Full Breakdown

Shoreline layers its own procedural amendments onto the International Residential and Building Codes it adopts under Chapter 15.05 SMC. For one- and two-family construction, SMC § 15.05.040 rewrites Section R110.3 so that the permit card itself, once the building official (the city manager or a designee under SMC § 15.05.020(B)) signs the 'Final' inspection line, stands in as the certificate of occupancy; no separate certificate document is issued. Getting to that final signature requires the work to stay accessible and exposed for inspection at every stage the permit covers, since the standards of the adopted codes are enforced regardless of whether an earlier inspection already passed, and portions that fail an inspection must be corrected and cannot be covered until the inspector authorizes it.

A handful of minor projects skip the inspection cycle entirely: decks no more than 30 inches above grade, re-roofing that does not touch the roof diaphragm, and window replacement that does not change emergency escape openings are exempt from permit under Section R105.2 as Shoreline has amended it. On demolition permits, SMC § 15.05.015 requires the permit holder to request a site inspection once demolition is complete, and the permit itself is only valid 60 days from issuance unless the building official grants a 60-day extension for extenuating circumstances. Every inspection in this chapter is carried out by, or under the authority of, the city's building official.

Violations & Fines

Occupying a structure, or covering work, before the required inspection has been requested and approved is a violation of Shoreline's adopted building codes under Chapter 15.05 SMC. As with other Title 15 violations, the Director can issue a notice and order under SMC § 20.30.760 carrying a $500 civil penalty that escalates 150 percent every 14 days, and a willful violation is a misdemeanor punishable by up to $1,000 and 90 days in jail under SMC § 20.30.770. A demolition permit that lapses without the required final site inspection is void after 60 days unless extended.

Frequently Asked Questions

Does Shoreline issue a separate certificate of occupancy document?
No. Under SMC § 15.05.040's amendment to IRC Section R110.3, a dated, authorized signature entered on the permit card under the 'Final' inspection line constitutes the certificate of occupancy for one- and two-family construction; there is no separate certificate.
Can I cover work before the city inspects it?
No. Work is subject to inspection and must remain accessible and exposed until it is approved. Covering it early is a violation independent of whether the work itself meets code.
How long is a demolition permit valid in Shoreline?
SMC § 15.05.015 sets demolition permits to expire 60 days from issuance, with a single 60-day extension available if the building official approves extenuating circumstances, and requires the permit holder to request a site inspection once demolition is complete.

Sources & Official References

Other rules in Shoreline

All Shoreline rules

Compare Shoreline to another location·View the Washington building safety overview

Get notified when Building Inspections in Shoreline, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in King County handle building inspections.

Renton, WA
Some Restrictions
Kirkland, WA
Some Restrictions
Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions