Key Facts

Section
Caldwell City Code § 10-12-03-23
Mitigation tools
Setbacks, buffers, sound attenuation, hours
Fallback if unaddressed
Special Use Permit required
Named agencies
EPA, USDA, Southwest District Health, IDWR
Adopted
Ord. 3670, April 21, 2025

Summary

Caldwell regulates information and data center siting under City Code § 10-12-03-23. Operators must mitigate noise, vibration, and electromagnetic interference through setbacks, buffers, or operating hours, and the Director can force a Special Use Permit if those impacts cannot be adequately addressed.

10-12-03-23: INDUSTRY - INFORMATION / DATA CENTERS: (1) The following adverse effects shall be mitigated through setbacks, buffers, sound attenuation and/or hours of operation: A. Noise, odor, or vibrations detectable by the human senses without the aid of instruments. B. Radioactivity and electric or electromagnetic disturbances which unduly interfere with the normal operation of equipment, instruments, or appliances on abutting properties. C. Any other emission or radiation which endangers human health, results in damages to vegetation or property, or which exceed health and safety standards. D. In the event the Director determines that the applicant cannot adequately address such impacts, the use shall be subject to a Special Use Permit. (2) Application materials shall depict compliance with any applicable federal, state, or local standards regarding such use, including, but not limited to, those of the U.S. Environmental Protection Agency, the U.S. Department of Agriculture, Southwest District Health Department, and Idaho Department of Water Resources.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 Code: Local legislation current through Ordinance 3747, passed 3-16-2026).

Full Breakdown

Section 10-12-03-23 of the Caldwell City Code, adopted by Ordinance 3670 on April 21, 2025, is the specific-use standard for Industry - Information / Data Centers within Chapter 10's zoning framework. The section requires adverse effects to be mitigated through setbacks, buffers, sound attenuation, or hours of operation rather than left unaddressed. Three categories of impact are named directly: noise, odor, or vibration detectable by human senses without instruments; radioactivity and electric or electromagnetic disturbances that unduly interfere with equipment or appliances on abutting properties; and any other emission or radiation that endangers human health or damages vegetation, property, or exceeds health and safety standards.

If the Director determines an applicant cannot adequately address these impacts through the standard site design tools, the data center use is bumped out of by-right approval and made subject to a Special Use Permit, which brings public hearing review before it can proceed. S. S. Department of Agriculture, the Southwest District Health Department, and the Idaho Department of Water Resources as the specific agencies whose requirements the application materials must address. That agency list signals the kind of large-scale industrial impacts, water use, emissions, and waste handling, the code anticipates from data center facilities, and ties the local zoning review directly to those outside regulators' standards rather than setting independent numeric limits of its own for water or power consumption.

Violations & Fines

A data center that generates noise, vibration, or electromagnetic interference beyond what setbacks and buffers control, or that fails to document compliance with EPA, USDA, Southwest District Health Department, or Idaho Department of Water Resources standards, is out of compliance with Section 10-12-03-23 and can be required by the Director to obtain a Special Use Permit or correct the impact before continuing operation.

Frequently Asked Questions

Does Caldwell require a special permit for a data center?
Only if the Director decides the applicant cannot adequately mitigate noise, vibration, or electromagnetic impacts through setbacks, buffers, or hours of operation. Section 10-12-03-23 then requires the data center to go through the Special Use Permit process instead of by-right site plan approval.
What agencies review a data center's environmental impact in Caldwell?
Section 10-12-03-23 requires application materials to show compliance with federal, state, and local standards from the U.S. Environmental Protection Agency, the U.S. Department of Agriculture, the Southwest District Health Department, and the Idaho Department of Water Resources before the use can be approved.
What impacts does Caldwell's data center ordinance target?
Section 10-12-03-23 names three: noise, odor, or vibration detectable without instruments; electric or electromagnetic disturbances that interfere with equipment on neighboring properties; and any emission or radiation that endangers health or damages property or vegetation, all mitigated through setbacks, buffers, or operating hours.

Sources & Official References

Other rules in Caldwell

All Caldwell rules

Compare Caldwell to another location·View the Idaho data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Caldwell, ID changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.