Shreveport, LA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Residential buffer trigger
200 feet requires special use permit
Size cap, C-3/C-4
40,000 sf by right
Size cap, I-MU/OR
80,000 sf by right
Equipment rule
Cooling/power gear must be enclosed
Approving body
Metropolitan Planning Commission

Summary

Shreveport's UDC treats data centers as a zoning use limited by size and distance to housing. Section 6.1.L requires a special use permit for any data center within 200 feet of a residential district, caps size at 40,000 square feet in the C-3 and C-4 commercial districts and 80,000 square feet in the I-MU and OR districts, and requires all cooling and power equipment to be fully enclosed.

L.Data Center1.All data centers shall only operate in allowable zoning districts as indicated on the Use Matrix in Article 5 of this Code. Any data center located within 200 feet of a residentially zoned district shall require a special use permit approved by the Metropolitan Planning Commission.2.In all allowable zoning districts, all equipment necessary for cooling, ventilating, or otherwise operating the facility must be contained within an enclosed building where the use is located... 3.In the C-3 and C-4 Districts, the maximum permitted size is 40,000 square feet in gross floor area. However, this size limit may be exceeded as part of special use permit approval.4.In the I-MU and OR District, the maximum permitted size is 80,000 square feet in gross floor area. However, this size limit may be exceeded as part of a special use permit approval.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 85 Update 1 | Unified Development Code: Supplement 20).

Full Breakdown

Data centers get their own operating standard in UDC Section 6.1.L, on top of the district-by-district permission in the Table 5-1 Use Matrix, where a 'P/S' designation means the outcome depends on the facility's size and its distance to housing. Any data center within 200 feet of a residentially zoned district needs a special use permit approved by the Metropolitan Planning Commission, regardless of how large it is.

Size caps apply in two zoning categories. In the C-3 and C-4 commercial districts, a data center is capped at 40,000 square feet of gross floor area as a permitted use; a facility that wants to exceed that size can only do so through special use permit approval from the MPC. In the I-MU Industrial Mixed-Use and OR Office Research districts, the cap doubles to 80,000 square feet, again with special use approval available for anything larger.

Every data center, in every allowable district, must contain all equipment used for cooling, ventilating, or otherwise operating the facility, including emergency generators and backup power supply equipment, inside an enclosed building; outdoor cooling towers or generator yards are not permitted regardless of district or size. Data Center is defined in Section 5.3 as a facility used primarily for storing, managing, processing and transmitting digital data, including the servers, power generation, water cooling, and utility infrastructure needed to keep it running.

Violations & Fines

Building or expanding a data center past its 40,000 or 80,000-square-foot cap, placing one within 200 feet of housing, or running cooling or generator equipment outdoors without MPC special use approval violates UDC Section 6.1.L, enforced by the Zoning Administrator under Article 19 with a Code of Ordinances Section 1-14 fine of up to $1,000.00 or 60 days imprisonment per day of violation.

Frequently Asked Questions

How close can a data center be to a house in Shreveport?
Closer than 200 feet only with a special use permit. UDC Section 6.1.L requires Metropolitan Planning Commission approval for any data center located within 200 feet of a residentially zoned district, regardless of the facility's size, before it can be built.
How big can a data center be without a special permit?
It depends on the district. Section 6.1.L caps by-right data centers at 40,000 square feet of gross floor area in the C-3 and C-4 commercial districts and at 80,000 square feet in the I-MU and OR districts. Anything larger needs special use permit approval from the Metropolitan Planning Commission.
Can a data center run its generators or cooling outdoors?
No. Section 6.1.L requires that all equipment used for cooling, ventilating, or otherwise operating a data center, including emergency power generators and backup supply equipment, be contained within an enclosed building in every zoning district where the use is allowed.

Sources & Official References

Other rules in Shreveport

All Shreveport rules

Compare Shreveport to another location·View the Louisiana data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Shreveport, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.