Blaine, MN Environmental Rules: Erosion Control (2026)
Key Facts
- Plan trigger
- Land disturbance over 20,000 sq ft
- Required plan
- Grading, erosion & sediment control plan
- SWPPP inspection
- Every 7 days, plus after 0.5" rain
- Enforcement tool
- City may issue a stop-work order
- Cost recovery
- City can bill owner's financial security
- Citation
- Blaine City Code § 129-24
Summary
In the City of Blaine, any land-disturbing project bigger than 20,000 square feet must get city approval for a grading, erosion and sediment control plan before work starts, under Sec. 129-24. The rule folds in a stormwater pollution prevention plan and lets the city issue stop-work orders when a site's erosion controls fail.
(f)General criteria. The grading, erosion and sediment control plan shall be required for any land disturbance activity or project disturbing more than 20,000 square feet and shall minimize exposed soil and unstable soil conditions in area and duration, disturbance of natural soil cover and vegetation, work in and adjacent to water bodies and wetlands, off-site sediment transport by trucks and equipment, and disturbance to the surrounding soils, root systems and trunks of trees adjacent to site activity that are intended to be left standing. ... (4)Failure to do corrective work. When an applicant fails to conform to any provision of this policy within the time stipulated, the city may take one or more of the following actions:a.Issue a stop work order, withhold the scheduling of inspections, or the issuance of a certificate of occupancy.
Full Breakdown
Blaine's soil erosion and sedimentation control ordinance, Sec. 129-24, requires a grading, erosion and sediment control plan for any land disturbance activity or project that disturbs more than 20,000 square feet. The plan has to minimize exposed soil, disturbance to natural cover, and off-site sediment tracking, and it must protect receiving waters, wetlands, and storm sewer inlets from sediment. Projects also have to comply with the city's municipal separate storm sewer system (MS4) permit and, where applicable, a federal NPDES construction stormwater permit, and every applicant must submit a stormwater pollution prevention plan, or SWPPP, alongside the grading plan.
Once work begins, the SWPPP's designated trained contact must inspect the site at least once every seven days during active construction and again within 24 hours of any rainfall of a half inch or more in 24 hours. City engineering staff also conduct their own inspections before work starts, at project completion, and before releasing any financial security posted for the project. If the city finds a site is not meeting its SWPPP, it can issue a stop-work order, withhold inspections or a certificate of occupancy, correct the deficiency itself or hire a contractor to do it, and bill the property owner or draw against the posted financial security for the cost. Costs not paid within 30 days of the city incurring them come out of that financial security.
Violations & Fines
Noncompliance under Sec. 129-24(n)(4) lets the city issue a stop-work order and withhold inspections or a certificate of occupancy until the erosion controls are fixed, and the city may correct the deficiency itself and bill the owner, drawing on the project's financial security if payment is not made within 30 days. Because Sec. 129-24 is part of the Code, the general penalty in Sec. 1-7, up to a $1,000.00 fine and 90 days in jail, also applies to a knowing violation.
Frequently Asked Questions
Do I need an erosion control plan for a small addition in Blaine?
How often does an erosion control plan get inspected during construction in Blaine?
What can the city do if my construction site's erosion controls fail?
Sources & Official References
Other rules in Blaine
Compare Blaine to another location·View the Minnesota environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.