Brookhaven, GA Environmental Rules: Erosion Control (2026)
Key Facts
- Governing section
- Brookhaven Code § 14-29
- Permit issuing office
- Community development department
- Permit decision deadline
- Not later than 45 days after a completed application
- Maximum bond
- $3,000.00 per acre or fraction thereof
- Stream buffers
- 25 feet on state waters, 50 feet on trout streams
- Civil penalty
- Not to exceed $1,000.00 per day
Summary
In the City of Brookhaven, Georgia, Sec. 14-29 requires a permit from the community development department before any land-disturbing activity, with an erosion and sedimentation control plan, per-acre fees, an optional bond up to $3,000.00 per acre, stream buffers of 25 and 50 feet, and civil penalties not to exceed $1,000.00 per day.
(1)General requirements. Any land-disturbing activity permitted under this chapter shall be carried out in accordance with the Georgia Erosion and Sedimentation Act of 1975, as amended; this chapter; and the permit conditions specified by the community development director. ... 1.No person shall conduct any land-disturbing activity within the jurisdictional boundaries of city without first obtaining a permit from the community development department to perform such activity, and providing a copy of the notice of intent, if applicable, to the EPD. ... d.Monetary penalties. Any person who violates any provisions of this section, or any permit condition or limitation established pursuant to this section, or who negligently or intentionally fails or refuses to comply with any final or emergency order of the community development department issued as provided in this section shall be liable for a civil penalty not to exceed $1,000.00 per day, and may be subject to the provisions of section 1-11. Each day during which violation or failure or refusal to comply continues shall be a separate offense.
Full Breakdown
Section 14-29 of the Code of the City of Brookhaven, Georgia governs soil erosion and sedimentation control for land-disturbing activity. Under subsection (b)(1), any permitted activity must follow the Georgia Erosion and Sedimentation Act of 1975, the chapter, and the permit conditions set by the community development director. Nobody can start land disturbance without a permit from the community development department and, where applicable, a copy of the notice of intent to the EPD. The application needs an erosion and sedimentation control plan and a certification that the plan preparer visited the site first.
The permit fee is set by the city council for each acre or fraction thereof, and state fees cannot exceed $80.00 per acre. The district reviews the plan within 35 days, and permits are issued or denied not later than 45 days after a completed application. The department can require a bond up to $3,000.00 per acre or fraction thereof and can deny an applicant with two or more violations in the prior three years. A development permit is valid for two years and expires if work has not begun within 90 days.
Exemptions include surface mining, home gardens and minor landscaping, agricultural operations, forestry practices, and single-family homes disturbing less than one acre outside a larger common plan. A project under one acre is still covered when it sits within a larger common plan of development of one acre or more or within 200 feet of the bank of state waters. Subsection (b)(4)c establishes a 25-foot state buffer along the banks of state waters and a 50-foot buffer along trout streams. A discharge that raises the turbidity of receiving waters by more than 25 nephelometric turbidity units for warm water fisheries, or by more than ten for trout waters, is a separate violation for each day.
Violations & Fines
For the first and second violations on a site, the community development department issues a written notice and the violator has five days to correct it before a stop work order issues. An imminent threat to public health or state waters draws an immediate stop work order, as does every third and later violation. Section 14-29(b)(7)d sets a civil penalty not to exceed $1,000.00 per day, each day a separate offense, and a failure to comply can forfeit the performance bond.
Frequently Asked Questions
Do I need a permit for a small project in Brookhaven?
How long does a land disturbance permit take?
What stream buffers apply?
How do I appeal a suspended or revoked permit?
Sources & Official References
Other rules in Brookhaven
Compare Brookhaven to another location·View the Georgia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.