Cecil County, MD Environmental Rules: Erosion Control (2026)
Key Facts
- Permit trigger
- 100+ cubic yards moved or 5,000+ sq ft disturbed
- Issuing agency
- Cecil County Department of Public Works
- Plan approval
- Cecil Soil Conservation District
- Permit validity
- 1 year, one 6-month extension available
- Max criminal fine
- $10,000 plus up to 1 year jail, per day
- Civil damages
- Double the cost of required controls
- Bond waiver
- Projects under $5,000
Summary
Any land-disturbing project in unincorporated Cecil County that moves 100 or more cubic yards of earth or disturbs 5,000 or more square feet needs a Department of Public Works grading permit backed by a Cecil Soil Conservation District-approved erosion and sediment control plan.
A grading permit, issued by the Cecil County Department of Public Works, shall be required prior to the start of any development or activity where such proposed development or activity may, in the judgment of DPW: ... Introduce sediment into any watercourse of the county or state; or ... Move one hundred (100) or more cubic yards of earth or disturb 5,000 square feet or more of land area; or ... Create undue erosion and sediment damage to lands adjacent to or in the vicinity of the subject site or the stream itself. ... Any person who violates any provision of this chapter is guilty of a misdemeanor and upon conviction in a court of competent jurisdiction is subject to a fine not exceeding $10,000 or imprisonment not exceeding one year, or both, for each violation, with costs imposed in the discretion of the court. Each day upon which the violation occurs constitutes a separate offense.
Full Breakdown
Cecil County Code § 312-10 requires a grading permit from the Department of Public Works before starting any development or activity that, in DPW's judgment, could introduce sediment into a watercourse, move 100 or more cubic yards of earth or disturb 5,000 or more square feet of land, or create undue erosion and sediment damage to nearby land or streams. No grading permit can issue without an erosion and sediment control plan already approved by the Cecil Soil Conservation District, and no building permit can issue without a valid grading permit unless the activity is exempt.
01, the 2011 Maryland Standards and Specifications and the Stormwater Management Act of 2007, and applies it to all land grading in the county. A grading permit runs one year from issuance under § 312-11, with one six-month extension available if requested a month before expiration. Fees for grading permits, reinstatements and inspections are set by County Council resolution under § 312-12. Section 312-16 requires the owner or developer to post a surety or cash bond, letter of credit, or other DPW-approved security equal to the cost of installing, maintaining and removing the approved erosion controls, waivable only for projects under $5,000, state or County-funded work, or standard plans for minor disturbances.
I. DPW can suspend or revoke a grading permit under § 312-13 for plan violations, noncompliance with a stop-work order, or changed site conditions, and must stop work outright wherever land disturbance occurs without an approved plan or active permit under § 312-21.
Violations & Fines
Violating any provision of Chapter 312 is a misdemeanor under § 312-22.A, punishable by a fine of up to $10,000 or imprisonment of up to one year, or both, with each day of violation charged as a separate offense. A person who fails to install or maintain required erosion controls is also liable in a civil action for double the cost of installing or maintaining those controls, and DPW may suspend, withdraw or deny grading and building permits until corrective action is completed.
Frequently Asked Questions
How much earthwork triggers a grading permit in Cecil County?
Who approves the erosion and sediment control plan in Cecil County?
What happens if I violate Cecil County's erosion control chapter?
Sources & Official References
Other rules in Cecil County
Compare Cecil County to another location·View the Maryland environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.