Greece, NY Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger threshold
1 acre or more of disturbance
Reviewing officer
Stormwater Management Officer
Sediment removal trigger
50% of trap/pond capacity
Closeout vegetation cover
80% perennial cover, full site
Max penalty
$1,000 fine or 1 year jail, per day

Summary

Greece requires a stormwater pollution prevention plan approved by the Stormwater Management Officer before disturbing one acre or more of land, following NYSDEC erosion and sediment control standards. Violations bring a stop-work order and fines up to $1,000 per day.

This article shall be applicable to all land disturbance activities that will disturb one or more acre of land unless exempted under § 176-19B of this article. ... Any applicant requesting site plan approval or a permit for land disturbance activity which would require the disturbance of one or more acres of land shall also include with a submission a SWPPP that shall be reviewed and approved by the Stormwater Management Officer prior to issuance of the final site plan approval or a permit. ... Any person who fails to comply with any provision of this chapter ... shall, upon conviction, be punished by a fine of not more than $1,000 or by imprisonment not to exceed one year, or both.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4702072; v22 updated 2025-08-21; through 08-21-2025).

Full Breakdown

Chapter 176, Article III governs land disturbance activity in the Town. Under § 176-16, the article applies to any land disturbance of one or more acres, including smaller phases of a larger common plan of development that together reach one acre. Section 176-18 requires erosion and sediment controls that meet the NYSDEC's Standards and Specifications for Erosion and Sediment Control, and postconstruction runoff controls that meet the NYS Stormwater Management Design Manual; any deviation must be shown equivalent and the SWPPP prepared by a licensed or certified professional.

Under § 176-19, an applicant for site plan approval or a land disturbance permit covering one acre or more must submit a stormwater pollution prevention plan (SWPPP) for review and approval by the Stormwater Management Officer before final approval issues, plus a filing fee under § 176-24. Emergency activity and defined agricultural activity are exempt under § 176-19B. During construction, § 176-23 requires sediment to be removed from traps or ponds once their capacity is reduced by 50%, and bars land disturbance that causes turbidity creating substantial visible contrast to natural surface water conditions.

Project closeout requires re-establishing 80% perennial vegetative cover over the full site, removing all temporary erosion controls, and a written certification of final stabilization by a licensed New York State professional before securities are released.

Violations & Fines

Under Article V, the Chief Engineer can issue a stop-work order under § 176-36 whenever work proceeds without a valid stormwater permit or violates the chapter, and can issue an appearance ticket under § 176-39. Section 176-40 sets the penalty at up to $1,000 or up to one year imprisonment, or both, per offense, with each day of continued noncompliance a separate offense.

Frequently Asked Questions

When does a Greece construction site need an erosion control plan?
Section 176-16 triggers the requirement at one acre or more of land disturbance, including smaller phases that are part of a larger common plan of development or sale reaching one acre. The plan is a stormwater pollution prevention plan (SWPPP) reviewed under § 176-19.
Who approves a SWPPP in the Town of Greece?
The Stormwater Management Officer reviews and approves the SWPPP under § 176-19 before final site plan approval or permit issuance, and the applicant must also submit a copy of any NYSDEC notice of intent for construction-activity coverage to the Department of Public Works.
What happens if a builder violates the erosion control rules?
The Chief Engineer can issue a stop-work order under § 176-36 and, under § 176-40, a violation is punishable by a fine of up to $1,000 or up to one year in jail, or both, with each day of continued violation counted separately.

Sources & Official References

Other rules in Greece

All Greece rules

New York rules heatmap·Compare Greece to another location·View the New York environmental rules overview

Get notified when Erosion Control in Greece, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Monroe County handle erosion control.

Rochester, NY
Some Restrictions