Hutto, TX Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Pre-work erosion controls
Silt fence required, § 18.03.054(a)(4)
Post-work stabilization deadline
14 days, § 18.03.006(b)(2)(D)
SWPPP for stream crossings
§ 18.03.053(c)(21)
Penalty
Class C misdemeanor, up to $500/day
Enforcing dept
City manager / engineering department

Summary

Contractors working in a Hutto public right-of-way must put erosion controls such as silt fencing in place before construction begins and stabilize any disturbed area from erosion within 14 days after the work is finished, under sections 18.03.053 and 18.03.054.

(4) Erosion control measures (e.g. silt fence) and advance warning signs, markers, cones and barricades must be in place before work begins. ... (7) Permittee shall be responsible for stormwater management erosion control that complies with city, state and federal guidelines. Requirements shall include, but not be limited to, silt fencing around any excavation that will be left overnight, silt fencing in erosion areas until reasonable vegetation is established, barricade fencing around open holes, and high erosion areas will require wire backed silt fencing. ... (D) Fail to stabilize any disturbed area from erosion within 14 days after construction is completed, unless an alternative timeframe is approved by the city.

Full Breakdown

Section 18.03.054(a)(4) requires that erosion control measures such as a silt fence, along with advance warning signs, markers, cones and barricades, be in place before any right-of-way work begins, and that barricades, warning signs and lights be placed wherever a pavement cut, excavation, or stockpiled soil creates a hazard. Subsection (a)(7) makes the permittee responsible for stormwater management erosion control that complies with city, state and federal guidelines, specifically requiring silt fencing around any excavation left overnight, silt fencing in erosion-prone areas until vegetation is reestablished, barricade fencing around open holes, and wire-backed silt fencing in high-erosion areas.

On the back end, section 18.03.006(b)(2)(D) separately makes it an offense to fail to stabilize a disturbed area from erosion within 14 days after construction is completed, unless the city approves an alternative timeframe. Section 18.03.053(c)(21) folds in the stormwater side: where a permit involves an open-cut stream crossing, the permittee must submit two sets of a Stormwater Pollution Prevention Plan (SWPPP) to the city, and in every other case must implement erosion control measures in accordance with the code's Stormwater Pollution Control article as well as other Hutto ordinances and state or federal law.

Failing any of these requirements exposes the permittee to the article's general enforcement scheme: a class C misdemeanor under section 18.03.006(a), each day of the violation a separate offense, a fine up to $500.00 (or up to $2,000.00 if a culpable mental state is alleged), plus civil remedies and denial of future right-of-way permits until the city's costs are reimbursed and the violation corrected.

Violations & Fines

Damaging the right-of-way beyond what construction requires, or failing to stabilize a disturbed area from erosion within 14 days of completing work, is an offense under section 18.03.006, a class C misdemeanor punishable by a fine up to $500.00 per day (up to $2,000.00 with an alleged culpable mental state), with civil action and permit denial available to the city as well.

Frequently Asked Questions

When must erosion controls be installed for right-of-way work in Hutto?
Before construction begins. Section 18.03.054(a)(4) requires erosion control measures, such as a silt fence, and advance warning devices to be in place before work starts, with additional silt fencing required around excavations left overnight and in high-erosion areas.
How long do I have to stabilize disturbed soil after right-of-way work in Hutto?
14 days after construction is completed, under section 18.03.006(b)(2)(D), unless the city approves an alternative timeframe. Failing to do so is a separate offense under the same enforcement article.
Does Hutto require a stormwater plan for construction near streams?
Yes. Section 18.03.053(c)(21) requires the permittee to submit two sets of a Stormwater Pollution Prevention Plan when a right-of-way permit involves an open-cut stream crossing, and to implement erosion controls under the code's Stormwater Pollution Control article in all other cases.

Sources & Official References

Other rules in Hutto

All Hutto rules

Texas rules heatmap·Compare Hutto to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Hutto, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Williamson County handle erosion control.

Cedar Park, TX
Some Restrictions
Round Rock, TX
Some Restrictions