Montebello, CA Environmental Rules: Erosion Control (2026)
Key Facts
- Rainy season window
- November 15 to April 15
- Plan approval deadline
- November 1
- Device installation deadline
- November 15
- Slope planting trigger
- Cut over 5 ft, fill over 3 ft
- Administering official
- Montebello city engineer
- Default remedy
- Bond funds plus 10% surcharge
Summary
In the City of Montebello, grading work that continues into the rainy season, November 15 through April 15, must be protected by temporary erosion control devices under Montebello Municipal Code § 15.48.470. Plans need engineering department approval by November 1, and every device, including desilting basins, must be installed by November 15.
A.No fill material shall be placed, spread or rolled at such time or times that weather conditions are considered unfavorable by the city engineer. ... B.The period between November 15th and April 15th is determined to be the period during which heavy rainfall normally occurs in the city. Previously authorized grading work which continues into the rainy season shall be protected by the installation of temporary erosion control devices. Plans for erosion control devices shall be submitted to the engineering department and design approval obtained not later than November 1st. The design and construction of desilting basins which discharge drainage onto the city streets or natural watercourses shall be under the control of the engineering department. All temporary erosion control devices, including the desilting basins, shall be installed not later than November 15th.C.Grading work shall be limited or ceased if the city engineer finds that its continuance will constitute a hazard to person or property during the period November 15th through April 15th.
Full Breakdown
Chapter 15.48, Grading, treats November 15th through April 15th as the period during which heavy rainfall normally occurs in the city under § 15.48.470(B), and any grading work that was authorized earlier but continues into that window must be protected with temporary erosion control devices. The plans for those devices must go to the engineering department for design approval no later than November 1st, and the devices themselves, including any desilting basin that discharges drainage onto city streets or natural watercourses, must be installed no later than November 15th, with the design and construction of desilting basins kept under the engineering department's direct control.
Subsection A separately bars placing, spreading or rolling fill material whenever the city engineer considers the weather unfavorable, and once heavy rain interrupts work, fill operations cannot resume until the soils engineer's field tests show the moisture content and density again meet chapter requirements. Subsection C lets the city engineer limit or stop grading entirely during the rainy season if continuing would create a hazard to people or property. The chapter pairs the seasonal rule with a permanent planting requirement in § 15.48.480, which requires cut slopes over five feet and fill slopes over three feet to be planted with grass or groundcover, plus shrubs or trees on slopes over fifteen feet, with an approved irrigation system, before the grading bond is released.
All drainage from cut and fill slopes must run through nonerosive facilities to the nearest street, storm drain or natural watercourse under § 15.48.500, and property owners must keep every drainage and protective device in good repair under § 15.48.550.
Violations & Fines
Missing the November 1st design-approval deadline or the November 15th installation deadline for temporary erosion control devices is a default under the grading permit, enforceable under § 15.48.510: the city engineer can order the required work performed or, if a bond was posted, use the bond funds, plus a ten percent administrative surcharge, to complete the work itself. The city engineer can also order grading halted outright under § 15.48.470(C) if continuing during the rainy season endangers people or property.
Frequently Asked Questions
By when must erosion control devices be installed on a Montebello grading site?
What counts as the rainy season for Montebello grading rules?
Can grading continue during a heavy rainstorm in Montebello?
What happens if I miss the erosion control deadlines on my grading permit?
Sources & Official References
Other rules in Montebello
California rules heatmap·Compare Montebello to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.