Old Bridge, NJ Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Township Code § 250-91
Permit trigger
Over 5,000 sq ft of disturbance
Required certification
Erosion plan approved by SCD first
Application copies required
4 copies of erosion/sediment plan
Review deadline
30 days or deemed approved
Max fine for noncompliance
$2,000 plus up to 90 days

Summary

Old Bridge Township requires a land disturbance permit before clearing, grading or excavating more than 5,000 square feet, and every application must include a soil erosion and sedimentation control plan certified by the Freehold Soil Conservation District before the Township will issue it.

No clearing, grading, soil removal, excavating, landfill, stripping or the filling or alteration of any natural or man-made drainageways or other land disturbance area of more than 5,000 square feet of surface area of land or in a critical or sensitive area regardless of the surface area ... shall be undertaken in the Township until a land disturbance permit has been issued by the Director of the Department of Community Development, or his designee, unless the activity is exempt from the requirements of this section ... or unless the Director of the Department of Community Development, or his designee, has granted a waiver pursuant to the provisions of Subsection D. ... Every applicant shall, prior to any activity described herein, submit to the Township Department of Community Development an application for a land disturbance permit which shall include four copies of soil erosion and sedimentation control plans ... Prior to applying for a land disturbance permit, the applicant's soil erosion and sedimentation control plan must have been certified as approved by the SCD.

Full Breakdown

Old Bridge Township Code § 250-91 bars clearing, grading, soil removal, excavating, landfilling, stripping, or altering natural or man-made drainageways on more than 5,000 square feet of land, or any amount in a critical or sensitive area, until the Director of the Department of Community Development issues a land disturbance permit or grants a waiver. In nonresidential zones, a permit is required for clearing regardless of size. Successive smaller disturbances that add up to more than 5,000 square feet within a two-year period are expressly prohibited unless each incident has its own permit.

Limited exemptions exist, including agricultural land under an approved farm conservation plan, lots of an acre or less with an existing residence (unless the disturbance is within 100 feet of a stream), and single-family construction not part of a larger development. Where a construction permit is also needed, the land disturbance permit application must be acted on first. To apply, an applicant must submit to the Department of Community Development four copies of soil erosion and sedimentation control plans identifying the property owner, a surveyed limit-of-disturbance line, and any trees of eight inches DBH or greater proposed for removal.

Before that application can be filed, the erosion and sedimentation control plan itself must already be certified as approved by the SCD, the Freehold Soil Conservation District, and proof of that certification must accompany the permit application. The Township reviews and must act within 30 days or the application is deemed approved, and a denial can be appealed to the approving board or Zoning Board of Adjustment within 10 days. The Director may issue a stop-construction order if work proceeds outside the approved plan.

Violations & Fines

Land disturbance violations fall under the Chapter 250 penalty structure. Township Code § 250-100 authorizes a fine of up to $2,000, imprisonment for up to 90 days, community service for up to 90 days, or a combination, with each continuing day of violation treated as a separate offense. Where unauthorized tree removal accompanies an unpermitted disturbance, § 250-91G requires the violator to submit a compensatory tree replacement plan within 30 days and post a performance guarantee, and failure to submit that plan on time is itself a separate daily offense.

Frequently Asked Questions

When does Old Bridge Township require a land disturbance permit?
A permit is required under Township Code § 250-91 before clearing, grading, excavating or filling more than 5,000 square feet of land, or any land disturbance at all in a critical or sensitive area or in a nonresidential zone.
Who must approve the erosion control plan before Old Bridge issues a permit?
The applicant's soil erosion and sedimentation control plan must first be certified as approved by the SCD, the Freehold Soil Conservation District, and proof of that certification must be filed with the land disturbance permit application under § 250-91D(2).
What happens if construction starts without the required permit in Old Bridge Township?
It is a Chapter 250 violation. Section 250-100 sets a penalty of up to $2,000, up to 90 days of imprisonment or community service, or both, with each day the violation continues counted as a separate offense, and the Director can issue a stop-construction order.

Sources & Official References

Other rules in Old Bridge

All Old Bridge rules

Compare Old Bridge to another location·View the New Jersey environmental rules overview

Get notified when Erosion Control in Old Bridge, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.