Stafford Township, NJ Environmental Rules: Erosion Control (2026)
Key Facts
- Certifying body
- Ocean County Soil Conservation District
- Review period
- 30 days, extendable by 30 days in writing
- If the District is silent
- Failure to decide within the period constitutes certification
- Applies to
- New construction of a primary structure
- Exemption
- Disturbance exceeding 5,000 square feet where the District has jurisdiction
- Penalty
- In accordance with N.J.S.A. 4:24-53
Summary
In Stafford Township, no site can be disturbed for new construction of a primary structure until the Ocean County Soil Conservation District certifies a soil erosion and sediment control plan. The District reviews within 30 days of a complete application, and a missed deadline counts as certification.
A. No site shall be disturbed by any person, partnership, corporation, special agency or other entity within this municipality unless an application for certification of a soil erosion and sediment control plan has been submitted to the District and such application and plan have been certified by the District, except as hereinafter exempted. ... C. Said application process shall only apply to new construction of a primary structure and shall not be required for any accessory structure or use incidental to the primary structure or use.
Full Breakdown
Stafford's erosion rules sit in Chapter 178, the Stafford Township Soil Erosion Ordinance (§ 178-1). Section 178-2 states the purpose of controlling soil erosion and sediment damage by requiring adequate provisions to prevent erosion and protect exposed soil surfaces, and directs that the Ocean County Soil Conservation District implement the chapter on behalf of the Township.
Section 178-5A bars disturbing any site until an application for certification of a soil erosion and sediment control plan has been submitted to the District and certified by it, except as exempted. Section 178-5C limits the application process to new construction of a primary structure, so an accessory structure or incidental use does not need it. The District must review within 30 days of a complete application, extendable by 30 days by written mutual agreement, and failure to decide in that time counts as certification (§ 178-5B). Its written notice says the plan was certified, certified with conditions, or denied with reasons, and a major revision counts as a new submission (§ 178-6). Fees follow the District's schedule (§ 178-9).
A plan under § 178-7 describes existing natural and man-made features including topography, soil characteristics and wetlands, the proposed changes, measures that meet or exceed the State Soil Conservation Committee standards, a schedule with starting and completion dates, and a map of existing and proposed contours. Section 178-8 sets field standards for any land disturbance: keep natural vegetation where feasible, keep the disturbed area and its exposure time within narrow limits, use temporary seeding, mulching or other stabilization on exposed critical areas, retain sediment on site to the maximum extent feasible, and install diversions and sediment basins before any on-site grading.
Exemptions in § 178-11 include home gardening, farming under an approved farm conservation plan, disturbance exceeding 5,000 square feet where the District has jurisdiction, clearing on a lot with an existing dwelling, and work permitted under Chapter 181. In the Pinelands, § 178-13 makes the Pinelands Comprehensive Management Plan prevail over any conflicting provision.
Violations & Fines
Under § 178-10A, a violation is punishable on conviction in accordance with N.J.S.A. 4:24-53, and § 178-10B allows summary abatement by restraining order or injunction. The District enforces the chapter and inspects the work (§ 178-12A). Where disturbance occurs without certification, it can issue a stop-work order and require the owner to apply; if certification is denied, the owner is responsible for reforestation under Chapter 130 or for permanent erosion control measures set by the District.
Frequently Asked Questions
Do I need erosion plan certification to build a shed in Stafford Township?
How long does the District take to certify a plan?
What must an erosion control plan contain?
What happens if land is disturbed without certification?
Sources & Official References
Other rules in Stafford Township
Compare Stafford Township to another location·View the New Jersey environmental rules overview