Compiled from the official code textEditor Martyn O'NeillLast verified November 2026

Key Facts

Certifying body
Ocean County Soil Conservation District
Review period
30 days, extendable by 30 days in writing
If the District is silent
Failure to decide within the period constitutes certification
Applies to
New construction of a primary structure
Exemption
Disturbance exceeding 5,000 square feet where the District has jurisdiction
Penalty
In accordance with N.J.S.A. 4:24-53

Summary

In Stafford Township, no site can be disturbed for new construction of a primary structure until the Ocean County Soil Conservation District certifies a soil erosion and sediment control plan. The District reviews within 30 days of a complete application, and a missed deadline counts as certification.

A. No site shall be disturbed by any person, partnership, corporation, special agency or other entity within this municipality unless an application for certification of a soil erosion and sediment control plan has been submitted to the District and such application and plan have been certified by the District, except as hereinafter exempted. ... C. Said application process shall only apply to new construction of a primary structure and shall not be required for any accessory structure or use incidental to the primary structure or use.

Full Breakdown

Stafford's erosion rules sit in Chapter 178, the Stafford Township Soil Erosion Ordinance (§ 178-1). Section 178-2 states the purpose of controlling soil erosion and sediment damage by requiring adequate provisions to prevent erosion and protect exposed soil surfaces, and directs that the Ocean County Soil Conservation District implement the chapter on behalf of the Township.

Section 178-5A bars disturbing any site until an application for certification of a soil erosion and sediment control plan has been submitted to the District and certified by it, except as exempted. Section 178-5C limits the application process to new construction of a primary structure, so an accessory structure or incidental use does not need it. The District must review within 30 days of a complete application, extendable by 30 days by written mutual agreement, and failure to decide in that time counts as certification (§ 178-5B). Its written notice says the plan was certified, certified with conditions, or denied with reasons, and a major revision counts as a new submission (§ 178-6). Fees follow the District's schedule (§ 178-9).

A plan under § 178-7 describes existing natural and man-made features including topography, soil characteristics and wetlands, the proposed changes, measures that meet or exceed the State Soil Conservation Committee standards, a schedule with starting and completion dates, and a map of existing and proposed contours. Section 178-8 sets field standards for any land disturbance: keep natural vegetation where feasible, keep the disturbed area and its exposure time within narrow limits, use temporary seeding, mulching or other stabilization on exposed critical areas, retain sediment on site to the maximum extent feasible, and install diversions and sediment basins before any on-site grading.

Exemptions in § 178-11 include home gardening, farming under an approved farm conservation plan, disturbance exceeding 5,000 square feet where the District has jurisdiction, clearing on a lot with an existing dwelling, and work permitted under Chapter 181. In the Pinelands, § 178-13 makes the Pinelands Comprehensive Management Plan prevail over any conflicting provision.

Violations & Fines

Under § 178-10A, a violation is punishable on conviction in accordance with N.J.S.A. 4:24-53, and § 178-10B allows summary abatement by restraining order or injunction. The District enforces the chapter and inspects the work (§ 178-12A). Where disturbance occurs without certification, it can issue a stop-work order and require the owner to apply; if certification is denied, the owner is responsible for reforestation under Chapter 130 or for permanent erosion control measures set by the District.

Frequently Asked Questions

Do I need erosion plan certification to build a shed in Stafford Township?
No. Section 178-5C says the application process applies only to new construction of a primary structure and is not required for any accessory structure or use incidental to the primary structure or use. A new house on a lot is the situation that brings in the Ocean County Soil Conservation District.
How long does the District take to certify a plan?
Section 178-5B requires review and certification within 30 days of a complete application, with one additional 30-day extension only by mutual written agreement between the District and the applicant. If the District makes no decision within that period or extension, the failure constitutes certification.
What must an erosion control plan contain?
Section 178-7 requires the existing features and soil characteristics, the proposed site changes, erosion measures meeting or exceeding the State Soil Conservation Committee standards, an installation schedule with start and completion dates, a before-and-after contour map, and anything else the District needs to evaluate the plan.
What happens if land is disturbed without certification?
Under § 178-12A the District can issue a stop-work order and require the owner to apply for certification. If certification is denied, the owner is responsible for reforestation under Chapter 130 or for permanent measures to control soil erosion and sedimentation as the District determines.

Sources & Official References

Other rules in Stafford Township

All Stafford Township rules

Compare Stafford Township to another location·View the New Jersey environmental rules overview

Get notified when Erosion Control in Stafford Township, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.