Whittier, CA Environmental Rules: Erosion Control (2026)
Key Facts
- Permit trigger
- 1+ acre of soil disturbance
- Emergency filing
- Description within 5 days, PRDs within 30
- Onsite records
- NOI, WDID number, SWPPP, inspection logs
- Record retention
- At least 3 years after completion
- Enforcing agency
- Public works director / authorized officers
- Base penalty
- Infraction, or misdemeanor by prosecutor's choice
Summary
Whittier requires any construction project disturbing one acre or more of soil by clearing, grading or excavating to first obtain a state NPDES construction general permit from the State Water Resources Control Board. Smaller construction jobs still must run erosion and sediment control best management practices pulled straight from the city's municipal stormwater permit tables, enforced by the public works director.
Construction activity not subject to the NPDES construction general permit that are subject to pollution control requirements under the municipal NPDES permit, shall implement BMPs prescribed by the regional board or its executive officer, or the city's public works director through programs or actions made pursuant to the municipal NPDES permit. This includes the implementation of an effective combination of erosion and sediment control BMP listed in table 7 and/or table 8 of the municipal NPDES permit, where applicable.
Full Breakdown
36 of the Whittier Municipal Code, the Stormwater and Runoff Pollution Control ordinance, splits construction sites into two tracks. 110, any site disturbing one acre or more must show the city it has obtained an NPDES construction general permit before work starts; the requirement carves out routine maintenance, agricultural disking and terracing, sites already under an individual NPDES permit, landfill construction under the industrial general permit, and combined-sewer discharges. A contractor who hits a public emergency requiring immediate work must file a brief description of the emergency activity within five days and submit the full permit registration documents within thirty days.
Permitted sites must keep a notice of intent, a waste discharge identification number, a stormwater pollution prevention plan and monitoring records on site, and retain them for at least three years after the job wraps, producing them on request from a city officer. 120 still requires an effective combination of erosion and sediment control BMPs drawn from Table 7 and Table 8 of the municipal NPDES permit, applied at the direction of the regional board, its executive officer, or Whittier's public works director. The public works director's authorized officers can inspect with consent or a warrant, collect samples, and demand monitoring reports at the property owner's expense.
Violations & Fines
Violating Chapter 8.36 is an infraction by default, though the city's enforcing attorney can file it as a misdemeanor instead; each day of noncompliance is a separate offense. The city can issue a notice of noncompliance with a compliance deadline of up to ninety days (extendable another ninety for good cause), or a cease-and-desist order, and can bill the violator for reinspection and enforcement costs. Continuing violations can be declared a nuisance under Government Code Section 38771, abated by the city, and recorded as a lien against the property under Government Code Sections 38773.1 and 38773.5.
Frequently Asked Questions
Does Whittier require an erosion control permit for small grading jobs?
What paperwork does a contractor need on a Whittier construction site?
What happens if I violate Whittier's construction stormwater rules?
Is there an exception for emergency construction work?
Sources & Official References
Other rules in Whittier
California rules heatmap·Compare Whittier to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in Los Angeles County handle erosion control.