Woodland, CA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Approving official
City Engineer
Trigger for state permit
1 acre or more disturbed soil
Required before
Grading or building permit issuance
SWPPP substitution
Allowed if it meets Chapter 8.08
Cost responsibility
Applicant pays City review/inspection fees

Summary

The City of Woodland, California requires anyone starting a construction activity to prepare and submit an erosion and sediment control plan before the City Engineer will issue a grading or building permit. The plan must identify site-specific best management practices, quantify expected soil loss, and list every other permit the project needs, under Municipal Code Section 8.08.070.

3. Erosion and Sediment Control Plan. The person who possesses the title of the real property or the leasehold interest of the premises on which a construction activity will occur within the City shall prepare and submit, or cause to be prepared and submitted, an erosion and sediment control plan prior to and as a condition of the issuance of a grading or building permit. The erosion and sediment control plan shall contain, at a minimum, appropriate site-specific construction site BMPs, the rationale used for selecting or rejecting BMPs, a quantification of expected soil loss where necessary, a list of applicable permits directly associated with applicable grading activity, and evidence that those permits have been obtained. No construction activity shall commence before the City Engineer issues written approval of the erosion and sediment control plan. A SWPPP developed pursuant to the construction general permit may substitute for the erosion and sediment control plan for projects where a SWPPP is developed.

Full Breakdown

Woodland Municipal Code Section 8.08.070(A) requires the owner of any property where a construction activity will occur, or the applicant's leasehold interest holder, to prepare and submit an erosion and sediment control plan before the City will issue a grading or building permit. The plan must contain, at minimum, site-specific construction best management practices drawn from CASQA's Construction Best Management Practice Manual or its equivalent, the rationale for selecting or rejecting those BMPs, a quantification of expected soil loss where necessary, and a list of every other permit tied to the grading activity along with proof those permits were obtained.

No construction activity may begin until the City Engineer issues written approval of the plan. A stormwater pollution prevention plan (SWPPP) prepared under the State's construction general permit can substitute for the erosion and sediment control plan on projects that already develop one, but the substitute SWPPP still must be submitted to the City for review and approval. Separately, Section 8.08.070(A)(2) requires any project disturbing one acre or more of soil, or part of a larger common plan of development disturbing one acre or more, to obtain coverage under the State Water Resources Control Board's construction general permit (NPDES No.

CAS000002) and to prove that coverage to the City Engineer before a grading or building permit issues. The City Engineer may also require additional structural BMPs under Section 8.08.070(A)(5) to keep pollutants from a construction site out of the MS4, and the applicant pays all City review and inspection costs under the master fee schedule.

Violations & Fines

Starting grading or construction without an approved erosion and sediment control plan, or without proof of construction general permit coverage where required, violates Chapter 8.08 and exposes the responsible party to a notice of violation, a stop-work cease-and-desist order, a fine up to the Government Code Section 36901 limit per violation, and recovery of the City's plan-review and inspection costs.

Frequently Asked Questions

Do I need an erosion control plan to build in Woodland?
Yes. Section 8.08.070(A)(3) requires the property owner or leaseholder to submit an erosion and sediment control plan before the City will issue a grading or building permit for any construction activity, and no work can start until the City Engineer approves the plan in writing.
What must a Woodland erosion and sediment control plan include?
At minimum it must list site-specific construction best management practices and the reasoning for choosing or rejecting them, quantify expected soil loss where necessary, and identify every other permit tied to the grading work along with proof those permits were already obtained, per Section 8.08.070(A)(3).
Can I use my state SWPPP instead of a separate Woodland erosion plan?
Yes. Section 8.08.070(A)(3) allows a stormwater pollution prevention plan developed under the State construction general permit to substitute for the local erosion and sediment control plan, but that SWPPP must still comply with Chapter 8.08 and be submitted to the City for review and approval.
Which projects in Woodland need the state construction general permit?
Any project that disturbs one acre or more of soil, or that disturbs less than one acre but is part of a larger common plan of development or sale totaling one acre or more, must obtain coverage under the State Water Board's construction general permit before the City issues a grading or building permit.

Sources & Official References

Other rules in Woodland

All Woodland rules

California rules heatmap·Compare Woodland to another location·View the California environmental rules overview

Get notified when Erosion Control in Woodland, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Yolo County handle erosion control.

West Sacramento, CA
Some Restrictions