Woodland, CA Parking Rules: EV Charging (2026)
Key Facts
- Governing section
- Woodland Municipal Code § 17.68.060
- 51+ space lots
- EV stations for 6% of total spaces
- 10-25 space lots
- One EV charging space required
- Minimum EVSE level
- Level 2 or higher
- Accessible EV space
- Van-accessible dimensions, built first
- Public station sign limit
- 4 sq ft, 8 ft height, nonilluminated
- Exceptions
- Insufficient power or housing hardship only
Summary
New buildings in the City of Woodland, California must install electric vehicle charging spaces under Woodland Municipal Code § 17.68.060, with minimums scaled to a project's total required parking: none under 10 spaces, one for 10 to 25, two for 26 to 50, and 6% of the total for 51 or more. The Planning and Building Director and Building Official may waive the standard only for insufficient electrical supply, adverse utility infrastructure cost impacts, or affordable-housing economic hardship.
§ 17.68.060. Electric Vehicle Charging Stations. Electric vehicle (EV) charging stations and EV-capable parking spaces shall be provided for all new buildings erected as required by this section. ... A. Required EV Charging Stations. The total number of required EV charging stations spaces are specified in Table 17.68.060.A-1: Required EV Charging Spaces.
Table 17.68.060.A-1: Required EV Charging Spaces Total Number of Required Parking Spaces Minimum EV Charging Spaces ... 51+ 6% of total
B. Exceptions. Exceptions to Table 17.68.060.A-1: Required EV Charging Spaces may be made on a case-by-case basis where the Planning and Building Director and the Building Official determine that EV charging infrastructure is not feasible based upon one or more of the following conditions: ... E. EV Charging Stations. EV charging stations shall be allowed within any zone subject to all applicable requirements of the Municipal Code in addition to the following: ... 8. EV Stations for Public Use. EV charging stations for public use must be visible from the right-of-way and illuminated during nighttime business hours.
Full Breakdown
Section 17.68.060 folds EV parking into the site's overall on-site parking count under § 17.68.030, so a project's EV total is calculated from its regular parking demand, not added on top. The table sets four tiers: 0 to 9 required spaces need no EV stations; 10 to 25 spaces need one; 26 to 50 spaces need two, whether the use is residential or nonresidential; and any lot with 51 or more required spaces must provide EV stations equal to 6% of the total. Subsection C sends the size of EV and EV-capable spaces to § 17.68.090, Parking Area Development and Design Standards, and specifies that the EV supply equipment itself cannot shrink the stall.
Subsection D requires at least one EV space with van-accessible dimensions under the California Building Code where accessible parking is required, and that space must be the first EV station built on the property, though its curb cannot carry accessible pavement markings. Subsection E layers on construction and equipment rules: charging construction must meet California Green Building Standards Code sections 5.106.5.3.1 and 5.106.5.3.2, the supply equipment (EVSE) must be Level 2 or higher, chargers must be listed and labeled by an approved testing agency, and the installation cannot conflict with existing infrastructure or create pedestrian or vehicular hazards, with any affected trees identified in advance.
Stations open to the public must be visible from the right-of-way, lit during nighttime business hours, and may carry a single nonilluminated identification sign up to four square feet and eight feet tall; each public station must post its voltage and amperage, hours of enforcement, usage fee, safety information, and a contact for reporting malfunctions.
Violations & Fines
Woodland Municipal Code has no charging-specific fine; a missing or undersized EV installation is enforced through Community Development's building permit review and, if unresolved, the code's general penalty at § 1.08.070: a misdemeanor punishable by up to six months in County Jail or a $1,000 fine, or prosecution as an infraction carrying $100 for a first offense, $200 for a second within a year, and $500 after that. The City may also issue administrative citations under Chapter 9.20, and each day of noncompliance counts as a separate offense.
Frequently Asked Questions
How many EV charging spaces does a new building in Woodland need?
Can a Woodland project skip the EV charging requirement?
What must a public EV charging station in Woodland post?
What charger type does Woodland require?
Sources & Official References
Other rules in Woodland
California rules heatmap·Compare Woodland to another location·View the California parking rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
EV Charging in Nearby Cities
How other cities in Yolo County handle ev charging.