Alpharetta, GA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Residential freeboard
- 3 feet above base flood elevation
- Non-residential freeboard
- 1 foot above base flood elevation
- Flood vent sizing
- 1 sq in of opening per sq ft of enclosed area
- Vent placement
- Bottom no higher than 1 foot above grade
- Certification required
- FEMA Elevation or Floodproofing Certificate
Summary
New residential construction in Alpharetta's future-conditions floodplain must sit at least three feet above the base flood elevation, or one foot above the future-conditions flood elevation if that is higher. This freeboard requirement, set in the Unified Development Code, exceeds the minimum federal flood insurance standard.
B.Building Standards for Structures and Buildings Within the Future-Conditions Floodplain.1.Residential Buildings.a.New construction. ... If all requirements of Sections 3.4.4.C, 3.4.4.D, and 3.4.4.E have been met, all new construction shall have the lowest floor, including basement, elevated no lower than three (3) feet above the base flood elevation or one (1) foot above the future-conditions flood elevation, whichever is higher. Should solid foundation perimeter walls be used to elevate the structure, openings sufficient to automatically equalize the hydrostatic flood forces on exterior walls shall be provided in accordance with standards of Subsection 3.4.5.A.5.
Full Breakdown
Section 3.4.5.B.1 requires that, once a residential project meets the no-rise and encroachment standards of Sections 3.4.4.C, 3.4.4.D, and 3.4.4.E, its lowest floor, including any basement, be elevated no lower than three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever is higher. This same three-foot freeboard applies to substantial improvements of existing residential structures and to new manufactured homes under Sections 3.4.5.B.1.b and 3.4.5.B.5. Non-residential structures get a one-foot freeboard standard instead under Section 3.4.5.B.2, with an option to floodproof to that same level rather than elevate, certified by a licensed professional engineer or architect using the FEMA Floodproofing Certificate.
Where solid foundation perimeter walls are used to reach the required elevation, Section 3.4.5.A.5 requires flood vents sized to provide at least one square inch of opening for every square foot of enclosed area below the lowest floor, with the bottom of each opening no higher than one foot above grade. Buildings located adjacent to, rather than inside, the future-conditions floodplain still face the same three-foot residential and one-foot non-residential freeboard under Section 3.4.5.C. The Directors of Community Development and Public Works record the actual elevation of every new and substantially improved structure and can require an as-built Elevation Certificate before occupancy.
Violations & Fines
A structure built below the required freeboard elevation is presumed to be in violation until an elevation certificate or other compliance documentation is provided, under the definition of Violation in Section 3.4.2. Section 3.4.7 allows the City to issue a stop-work order, withhold the certificate of occupancy, or impose civil penalties of up to $1,000 per day, with criminal citations carrying a fine of up to $1,000 or imprisonment for up to 60 days for intentional or flagrant violations.
Frequently Asked Questions
How high above base flood elevation must a new Alpharetta home be built?
Does Alpharetta's freeboard rule apply to commercial buildings too?
What if I use solid foundation walls to elevate my house in the floodplain?
Sources & Official References
Other rules in Alpharetta
Compare Alpharetta to another location·View the Georgia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Fulton County handle flood elevation requirements.