Key Facts

BFE defined
1% annual chance flood, Sec. 9-4.10(k)
Zone A/other zones
Lowest floor at or above BFE
Zone AO
Elevate to FIRM depth or 2 ft above grade
Certification
Registered engineer or licensed surveyor
Enforcing official
Flood Plain Administrator (Public Works Director)
Nonresidential option
Dry floodproofing instead of elevation

Summary

In Hayward's mapped flood hazard areas, Municipal Code Section 9-4.110(c) requires the lowest floor of new construction to sit at or above the base flood elevation, defined at Section 9-4.10(k) as the water-surface height reached by a flood with a one percent annual chance of occurring. The Flood Plain Administrator, the Director of Public Works, verifies elevation certifications before occupancy.

(k)Base flood elevation (BFE) means the elevation shown on the Flood Insurance Rate Map for Zones AE, AG, A1-30, VE, and V1-V30 that indicates the water surface elevation resulting from a flood that has a one percent (1%) or greater chance of being equaled or exceeded in any given year. [Sec. 9-4.110(c)(1)]: (ii)Zone A. In an A zone, the lowest floor shall be elevated to a level at or above the base flood elevation.(iii)All other FIRM Zones. In all other zones, the lowest floor shall be elevated to a height at or above the base flood elevation.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 28 Update 1 | Charter: Supplement 1).

Full Breakdown

10(k) defines base flood elevation (BFE) as the water surface elevation shown on the Flood Insurance Rate Map for Zones AE, AG, A1-30, VE and V1-V30 for a flood with a one percent or greater annual chance of being equaled or exceeded, commonly called the 100-year flood. 110(c) then sets the construction standard: in an AO zone, the lowest floor must be elevated to the depth number shown on the FIRM, or at least two feet above the highest adjacent grade if no depth number is given; in an A zone and in all other special flood hazard zones, the lowest floor must be elevated to a level at or above the base flood elevation.

A registered civil engineer or licensed land surveyor must certify the as-built elevation of the lowest floor, including any basement, and the City's community building inspector verifies it before the Flood Plain Administrator, the Director of Public Works, signs off. Non-residential structures may floodproof instead of elevate, making walls below the base flood level substantially impermeable and structurally able to resist hydrostatic and hydrodynamic loads, certified by a registered engineer or architect. Attached garages with a floor below the BFE must be built with flood-resistant materials and designed to let floodwater automatically enter and exit; small detached garages and accessory sheds may have a floor below the BFE only if built with flood-resistant materials below that line, anchored against flotation, and designed for automatic floodwater entry.

Violations & Fines

Section 9-4.03(f) makes these flood standards take precedence over any less restrictive local law, and the Flood Plain Administrator can deny a development permit outright for noncompliance in a mapped special flood hazard area. Building below the required base flood elevation without a certified floodproofing design exposes the owner to increased flood-insurance costs and, under Section 9-4.190, forfeits eligibility for a variance where it would cause fraud on or victimization of future owners.

Frequently Asked Questions

What is the base flood elevation in Hayward's flood code?
It's defined at Section 9-4.10(k) as the water surface elevation on the Flood Insurance Rate Map for a flood that has a one percent or greater chance of being equaled or exceeded in any year, also called the 100-year flood, for Zones AE, AG, A1-30, VE and V1-V30.
How high must I build above the base flood elevation in Hayward?
In a Zone A or any other FIRM zone besides AO, Section 9-4.110(c) requires the lowest floor to be at or above the base flood elevation itself, with no added freeboard specified. In a Zone AO, elevate to the FIRM's depth number or at least two feet above the highest adjacent grade.
Who certifies my home's elevation for Hayward's flood rules?
A registered professional civil engineer or licensed land surveyor must certify the as-built elevation of the lowest floor, and the community building inspector verifies it before the certification goes to the Flood Plain Administrator, who is the Director of Public Works, under Section 9-4.110(c)(1).

Sources & Official References

Other rules in Hayward

All Hayward rules

California rules heatmap·Compare Hayward to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Hayward, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Alameda County handle flood elevation requirements.