Huntington, NY Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Certification required by
- licensed professional engineer or land surveyor
- Datum used
- mean sea level
- Filed with
- Local Administrator (Dir. of Engineering Services)
- Trigger
- completion of the lowest floor
- Tied to
- issuance of certificate of occupancy
- Records retained under
- § 168-14(F)
Summary
Anyone building or substantially improving a structure in a Huntington flood hazard zone must document the actual finished elevation. A licensed professional engineer or land surveyor certifies the as-built lowest-floor elevation, referenced to mean sea level, and files it with the Town's Local Administrator.
(1) The proposed elevation, in relation to mean sea level, of the lowest floor (including basement or cellar) of any new or substantially improved structure to be located in Zones A1-A30, AE or AH, or Zone A, if base flood elevation data are available. Upon completion of the lowest floor, the permittee shall submit to the Local Administrator the as-built elevation, certified by a licensed professional engineer or surveyor.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4940543; v75 updated 2026-06-09; through 06-09-2026).
Full Breakdown
Town Code § 168-13(D)(1) requires floodplain development building permit applicants in Zones A1-A30, AE, AH or a data-backed Zone A to state the proposed elevation, relative to mean sea level, of the lowest floor, including any basement or cellar, and then, once the lowest floor is built, to submit the as-built elevation certified by a licensed professional engineer or surveyor. Coastal high hazard structures in Zones V1-V30 or VE follow the parallel requirement in § 168-13(D)(2), certifying the bottom of the lowest structural member instead.
The Local Administrator, the Director of Engineering Services, is the official who receives these certificates under § 168-14(C)(1), and the section warns that any further construction undertaken before that certification is submitted and reviewed proceeds at the permit holder's own risk; deficiencies found in the data are grounds for a stop-work order under § 168-14(C)(3) and § 168-39. Manufactured homes must have their certificate filed upon placement on site, and recreational vehicles staying 180 consecutive days or longer without a highway-ready license need one too.
Under § 168-14(F), the Town retains these as-built elevation certifications, along with floodproofing certificates and permit records, for public inspection. Section 168-14(E) ties the certificate of occupancy itself to this documentation: occupancy in a special flood hazard area cannot be authorized until the Local Administrator confirms compliance based on the certified elevations, inspections and any floodproofing or anchoring conditions attached to the permit.
Violations & Fines
Failing to obtain or file the required elevation certificate is an infraction of the permit conditions under § 168-40(A), punishable by a fine of $1,000 to $5,000, up to 15 days imprisonment, or both, with every day of continued non-compliance a separate offense. The Local Administrator may also withhold the certificate of occupancy and issue a stop-work order under § 168-39 until certified data is supplied.
Frequently Asked Questions
Who certifies the as-built flood elevation for new construction in Huntington?
When does the elevation certificate have to be submitted in Huntington?
Can I get a certificate of occupancy in a Huntington flood zone without it?
What happens if the elevation data shows the structure was built too low?
Sources & Official References
Other rules in Huntington
New York rules heatmap·Compare Huntington to another location·View the New York environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Suffolk County handle flood elevation requirements.