Key Facts

Base flood elevation
the 100-year flood elevation
Freeboard for rooms/basements
24 inches above base flood level
Freeboard for utility lines
24 inches, engineer-certified
LI District exception
at/above base flood level, no 24-in margin
LOMR trigger
any floodway rise, or >1 ft in Zone AE
LOMR deadline
within 6 months of the triggering work

Summary

Lower Merion Township defines base flood elevation as the 100-year flood elevation, and in the Schuylkill River floodway fringe it requires two feet of freeboard: every room, including basements, must sit at least 24 inches above that elevation, and utility lines must be floodproofed to the same 24-inch height.

BASE FLOOD ELEVATION The 100-year flood elevation. ... ... H. Schuylkill River Floodway Fringe. ... (4) Sewer, water and electric lines shall be floodproofed to a height of 24 inches above the base flood level. ... (5) Structures shall be constructed with all portions of all rooms, including basements, at least 24 inches above the base flood level. Exceptions include nonresidential structures in the Light Industrial (LI) District that may be constructed if all portions of all rooms, including basements, are constructed at or above the base flood level, and their associated sewer, water and electric lines are floodproofed to the base flood level.

Full Breakdown

Zoning Code § 155-2.1 defines BASE FLOOD ELEVATION simply as "the 100-year flood elevation," tied to the base flood itself, defined as the flood having a one-percent annual chance of being equaled or exceeded. Within the Schuylkill River Floodway Fringe, § 155-7.3H(4) requires sewer, water, and electric lines to be floodproofed to a height of 24 inches above the base flood level, certified by a Pennsylvania-registered professional engineer or architect and recorded with the Director of Building and Planning. Section 155-7.3H(5) requires that any permitted structure be built with all portions of all rooms, including basements, at least 24 inches above the base flood level, that two-foot freeboard margin above FEMA's minimum.

The only carve-out is for nonresidential structures in the Light Industrial District, which may sit at or above the base flood level itself, with their utility lines floodproofed to that lower elevation instead of the 24-inch standard. Separately, § 155-7.3B(2) requires anyone whose project would raise the base flood elevation to submit technical data to FEMA for a Letter of Map Revision, or a Conditional Letter of Map Revision if not yet built, no later than six months after the work that changed it, and a rise of more than one foot in Zones A1-30 or AE without a designated floodway triggers the same requirement.

A Zoning Officer permit is also required before any such map change takes effect, and the Township Manager submits the required annual National Flood Insurance Program report to FEMA under § 155-7.3J.

Violations & Fines

Freeboard and base-flood-elevation violations are enforced as zoning violations under § 155-11.4: a Zoning Officer enforcement notice sets a compliance deadline, and an owner who fails to elevate a structure or floodproof utility lines as required faces a civil judgment of up to $500 plus court costs and Township attorney fees before a Magisterial District Judge, with continuing daily violations after the fifth day.

Frequently Asked Questions

How high above the base flood elevation must my house be built in Lower Merion Township?
In the Schuylkill River floodway fringe, § 155-7.3H(5) requires every room, including basements, to sit at least 24 inches (two feet) above the base flood level. Utility lines serving the structure must be floodproofed to that same 24-inch height under § 155-7.3H(4), certified by a Pennsylvania-registered engineer or architect.
What is the base flood elevation, exactly?
Section 155-2.1 defines it as "the 100-year flood elevation," the water surface elevation reached by the base flood, which the code separately defines as the flood having a one-percent chance of being equaled or exceeded in any given year.
Is there any exception to the 24-inch freeboard rule?
Yes, for nonresidential structures in the Light Industrial District only. Under § 155-7.3H(5), those buildings may be constructed at or above the base flood level itself, with their sewer, water, and electric lines floodproofed to that lower elevation instead of the full 24-inch margin.

Sources & Official References

Other rules in Lower Merion

All Lower Merion rules

Compare Lower Merion to another location·View the Pennsylvania environmental rules overview

Get notified when Flood Elevation Requirements in Lower Merion, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Montgomery County handle flood elevation requirements.

Pottstown, PA
Some Restrictions