Lower Merion, PA Environmental Rules: Stormwater Management (2026)
Key Facts
- Governing chapter
- Ch. 121, Stormwater Management and Erosion Control
- Small-project exemption
- 1,500 sq ft or less added impervious cover
- Permit start deadline
- Work must start within 6 months
- Permit completion deadline
- Within 1 year of issuance
- Maximum fine
- $1,000 per offense
- Enforcing official
- Township Engineer
Summary
Chapter 121 requires every land development, subdivision, new building, or added impervious surface in Lower Merion Township to comply with a stormwater management and erosion control permit before work starts. Violations carry a fine of up to $1,000 per offense, with each continuing day a separate offense.
§ 121-2. Compliance required. ... A. Hereafter, no land shall be used, no earth shall be stripped or moved and no structure shall be built or extended without full compliance with the terms of this chapter and other applicable regulations. ... ... C. Regulatory activities. (1) The following activities are defined as "regulated activities" and shall be regulated by this chapter, except those that meet the waiver specifications presented thereafter: (a) Land development. (b) Subdivision. (c) Construction of new or additional impervious surfaces. (d) Construction of new buildings or additions to existing buildings. ... (2) Any proposed regulated activity ... which would create 1,500 square feet or less of additional impervious cover would be exempt from the requirements of this chapter regarding control of the peak rate of flow. ... ... § 121-28. Violations and penalties. ... Any person violating any of the provisions of this chapter shall be liable on conviction to a fine or penalty of not exceeding $1,000 for each and every offense ... each day that he shall continue such violation after notification shall constitute a separate offense punishable by a like fine or penalty.
Full Breakdown
Section 121-1 states the township's findings that inadequate stormwater management increases flooding, erosion, and sedimentation and burdens stream health, and sets the chapter's purpose of meeting water quality standards under 25 Pa. Code Chapter 93, preserving natural drainage, managing runoff near its source, maintaining groundwater recharge, and complying with the state's Act 167 stormwater studies. Section 121-2 makes compliance mandatory: no land may be used, no earth stripped or moved, and no structure built or extended without full compliance with the chapter, under authority the Pennsylvania Stormwater Management Act (Act 167 of 1978, as amended by Act 63 of 1984) grants the township.
Regulated activities include land development, subdivision, construction of new or additional impervious surfaces, construction of new buildings or additions, diversion or piping of a stream channel, installation of stormwater systems, and earthmoving. A regulated activity creating 1,500 square feet or less of additional impervious cover is exempt from peak-flow control, though the township can still require groundwater recharge or water quality compliance, and no waiver is available for stream diversion or stormwater system installation. Section 121-14 sets the permit fee under the township's Chapter A167 fee schedule, and Section 121-15 lets the Township Engineer attach conditions such as drainage structures, plantings, or easements before issuing a permit, with no permit issued until an approved runoff and erosion control plan is in place.
Permits under Section 121-16 expire if work has not started within six months or finished within one year, subject to an extension for unusual difficulties. Section 121-28 sets the penalty: a fine of not more than $1,000 for each offense, with each day a violation continues after notice from the Township Engineer a separate offense.
Violations & Fines
Undertaking a regulated activity, land development, subdivision, new impervious surface, or earthmoving, without an approved stormwater permit violates Section 121-2 and is punishable under Section 121-28 by a fine of not more than $1,000 per offense, with each day the violation continues after notice from the Township Engineer treated as a separate offense.
Frequently Asked Questions
Do I need a stormwater permit to add a driveway or addition in Lower Merion?
What is the penalty for stormwater violations in Lower Merion?
How long is a Lower Merion stormwater permit valid?
Sources & Official References
Other rules in Lower Merion
Compare Lower Merion to another location·View the Pennsylvania environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Stormwater Management in Nearby Cities
How other cities in Montgomery County handle stormwater management.