Conroe, TX Environmental Rules: Stormwater Management (2026)
Key Facts
- Permit trigger
- 1+ acre disturbed
- SWP3 threshold
- 5+ acres, state/federal rule
- Permit term
- 1 year, auto-expires
- Inspection interval
- Every 14 days / after 0.5" rain
- Criminal fine
- Up to $2,000/day
- Civil penalty
- Up to $1,000/day
Summary
Conroe requires a city stormwater permit and an engineer-prepared stormwater quality plan before any construction disturbing one acre or more can begin. Illicit discharges into the storm drain system are separately banned citywide.
A storm water permit shall be obtained prior to the start of any construction activity at a site by application to the director by the owner and/or operator of the construction site at which construction occurs or is proposed... Application for a storm water permit shall be submitted to the director, or their representative prior to beginning construction activities of any type, including clearing and leveling activities, for any construction site for which construction activities at the site will disturb in total one acre or more of land surface area. A storm water quality plan shall be submitted to, and approved by, the city building official prior to commencement of any construction activity at a construction site for which a storm water permit is required.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 85).
Full Breakdown
Article VIII of Chapter 26 regulates the city's municipal separate storm sewer system (MS4). Section 26-197 bars intentionally, knowingly, recklessly or negligently discharging anything into the storm drain system that violates water quality standards, with narrow exceptions such as landscape irrigation, pool draining and firefighting water, and separately bars illicit physical connections to the MS4. Section 26-198 requires anyone disturbing one acre or more of land, alone or as part of a common development, to obtain a stormwater permit from the director before starting work and to submit a stormwater quality plan prepared or approved by a Texas-licensed professional engineer describing best management practices for erosion and sediment control.
Sites of five acres or more that trigger a state or federal SWP3 requirement must also keep that plan on site. Permits are valid for one year, automatically expire, and construction must start within six months of issuance or the permit is void. 5 inches or more, keeping inspection reports on file. A site that sits idle for 14 continuous days without proper closure is itself a violation unless the operator shows the pause is temporary and the site is stabilized. The director can issue a stop work order under § 26-198(a)(3) that halts all activity, bars further permit approvals, and stays in effect until corrected deficiencies are inspected and cleared.
Violations & Fines
Section 26-203 makes any violation strictly liable, with criminal fines up to $2,000.00 per violation per day, plus a separate civil penalty of up to $1,000.00 per day under Local Government Code § 54.017 once the city proves the violator had notice and continued the violation. The city may also seek injunctive relief through the city attorney. Orders can be appealed in writing to city council within ten working days.
Frequently Asked Questions
When does a Conroe construction site need a stormwater permit?
Who can prepare Conroe's required stormwater quality plan?
What happens if a Conroe construction site sits inactive?
Sources & Official References
Other rules in Conroe
Texas rules heatmap·Compare Conroe to another location·View the Texas environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Stormwater Management in Nearby Cities
How other cities in Montgomery County handle stormwater management.