Key Facts

Enforcing official
Glynn County Engineer
Permit trigger
5,000 sq ft new impervious area or 1 acre disturbed
Design standard
County Local Design Manual (LDM)
Bond requirement
Construction cost plus 25 percent
Penalty
Up to $1,000 fine and/or 60 days jail per day
Appeal window
10 business days to County Administrator

Summary

Glynn County requires a land-disturbance permit and stormwater management plan for new development adding 5,000 square feet or more of impervious surface, or disturbing an acre or more of land. The Water Resources Protection Ordinance's Post Construction Runoff Control article sets the design standards the County Engineer enforces.

These county ordinances apply to unincorporated areas of Glynn County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

This ordinance shall be applicable to all development plan applications, unless eligible for an exemption pursuant to ordinance Section 2-27-23 below or granted a waiver by the County Engineer pursuant to ordinance Section 2-27-26 below. This ordinance also applies to the following land development activities: (a)New development that creates or adds 5,000 square feet or greater of new impervious surface area, or that involves land disturbing activity of one acre of land or greater; ... (a)Permit Required. Unless specifically excluded by Chapter 2-5, Article VII, a land disturbance activity requires a permit from Glynn County. No land owner or land operator shall receive any of the building, grading or other land development permits required for land disturbance activities without first meeting the requirements of this Article prior to commencing the proposed activity.

Full Breakdown

Chapter 2-27, the Water Resources Protection Ordinance, first bans illicit discharges into the county's separate storm sewer system (the CS4) of anything but stormwater, and bans illicit connections to it, enforced by the County Engineer with inspection authority and emergency suspension power. Article III's Post Construction Runoff Control provisions, added by Ordinance O-2021-04, apply to new development adding 5,000 square feet or more of new impervious surface, or one acre or more of land disturbance, to redevelopment of the same scale, and to any activity the County Engineer designates a stormwater hotspot; individual single-family or duplex lots outside a subdivision, and agricultural or silvicultural activity, are exempt.

Section 2-27-25 requires a land disturbance permit before any building or grading permit issues, an application meeting Chapter 2-5, Article VII's requirements, and an administrative review fee set by the Board of Commissioners. Design must follow the county's Local Design Manual, which supplements the Coastal Stormwater Supplement and Georgia Stormwater Management Manual, and a professional engineer licensed in Georgia must certify the stormwater management plan. The County Engineer may grant a waiver of the on-site requirements if alternative or off-site management provides equal control, and may require a performance bond of the construction cost plus 25 percent. Property owners must grant the county a perpetual maintenance easement and conduct annual inspections of stormwater facilities.

Violations & Fines

A violation may draw a written notice of violation from the County Engineer, appealable to the County Administrator within ten business days, and is deemed a public nuisance subject to a civil abatement action by the County Attorney. Any ordinance violation is punishable by a fine of not more than $1,000.00, or 60 days in jail, or both, with a separate offense for each day the violation continues, plus liability to the county for any resulting expense, loss or damage.

Frequently Asked Questions

Does building a new driveway trigger a Glynn County stormwater permit?
Only if it is part of new development or redevelopment adding 5,000 square feet or more of impervious surface, or one acre or more of land disturbance; a single-family lot addition outside a subdivision is exempt under Section 2-27-23.
Who reviews stormwater plans in Glynn County?
The County Engineer reviews and approves stormwater management plans and land disturbance permit applications, and no development permit issues until the plan or an approved waiver is on file.
Can a Glynn County stormwater requirement be waived?
Yes, the County Engineer may waive on-site stormwater management if the applicant shows the development will not impair the ordinance's objectives, or provides equivalent off-site or downstream capacity, subject to mitigation conditions.
What is the penalty for an illegal discharge into Glynn County's storm drains?
It is an ordinance violation punishable by a fine of up to $1,000.00 or 60 days in jail, or both, with each day the violation continues counted as a separate offense, in addition to nuisance abatement action.

Sources & Official References

Other rules in Glynn County

All Glynn County rules

Compare Glynn County to another location·View the Georgia environmental rules overview

Get notified when Stormwater Management in Glynn County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.