Lehi, UT Environmental Rules: Stormwater Management (2026)
Key Facts
- Governing chapter
- Lehi City Code ch. 9-3
- Adopted
- Ord. 99-2018, 11-13-2018
- First offense
- Class C misdemeanor
- Second offense
- Class B misdemeanor
- Correction window
- 48 hours to 10 calendar days
- Design requirement
- Utah registered PE seal required
Summary
Lehi regulates stormwater system design, construction, illicit discharges and inspections citywide under a dedicated 2018 ordinance built to satisfy NPDES/UPDES permit requirements. First offenses are class C misdemeanors, second offenses class B, plus civil penalties and cost recovery.
Design of storm drain systems within City boundaries and that discharge into a Lehi City storm drain system requires direct supervision of a Utah registered professional engineer, and shall carry the seal of the same supervising professional engineer. Site designs shall control the peak flow rates of stormwater discharge.
Full Breakdown
26 (§ 9-3-1). Section 9-3-3 requires stormwater system design and construction documents to conform to city-adopted standards and meet federal, state and local discharge quality requirements; storm drain design within city boundaries requires the direct supervision and seal of a Utah registered professional engineer, and site designs must control peak stormwater discharge flow rates using the LID Handbook's calculation methods. Section 9-3-4 requires erosion and sediment control on all construction activities under a stormwater construction permit, including a SWPPP submitted to and reviewed by the city before permit application, and requires post-construction revegetation on a schedule approved by the City Engineer.
Section 9-3-5 requires stormwater infrastructure on private land to carry recorded access easements binding on current and future owners for inspection and repair. Enforcement under § 9-3-7 lets the city issue notices of violation, stop-work orders, citations, compliance orders and cease-and-desist orders, with corrections generally required within 48 hours to 10 calendar days depending on severity as determined by a registered stormwater inspector. Penalties under § 9-3-8 escalate: a first offense may be charged as a class C misdemeanor, a second offense as a class B misdemeanor, both with fines assessable per day per violation, plus civil penalties set by council resolution in the consolidated fee schedule and recovery of the city's investigation, enforcement and maintenance costs, including attorney's fees. Aggrieved persons may appeal under § 9-3-9.
Violations & Fines
A first stormwater violation may be charged as a class C misdemeanor and a second offense as a class B misdemeanor under § 9-3-8, with fines assessed per day per violation; the city can also impose a civil penalty set by council resolution and recover its investigation, enforcement, maintenance and attorney's fee costs from the violator.
Frequently Asked Questions
Does Lehi require an engineer's stamp on stormwater system designs?
What happens on a first stormwater violation in Lehi?
How much time do I get to fix a cited stormwater violation?
Sources & Official References
Other rules in Lehi
Compare Lehi to another location·View the Utah environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Stormwater Management in Nearby Cities