Lehi, UT Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
over 1 acre disturbed or 2+ ft grade change
Control devices
sediment fences/basins before disturbance
Stormwater filing
SWPPP plus Utah DWQ Notice of Intent
Late/no-permit fine
$500 minimum per day
Permit term
1 year, extendable under §10.120
Issuing office
Public Works Director

Summary

Lehi requires a grading permit before disturbing more than one acre of land or moving more than two feet of fill or cut, and every permit application must map erosion and sedimentation control devices such as sediment fences and basins built before land-disturbing work begins.

A map of the subject area showing the location and type of erosion and sedimentation control devices. Some erosion is unavoidable. The resulting sediment must be trapped on the site, even during design flood conditions. Construct sediment fences and sediment traps and basins before other land-disturbing activities occur. Sediment fences, traps, and basins must be properly maintained, regularly inspected, and cleaned as necessary.

Full Breakdown

Development Code Chapter 12-B governs grading, filling and excavation. A grading permit is required for any grading, clearing or grubbing exceeding one acre (43,560 square feet), any fill or excavation changing elevation more than two feet from adjacent properties, or retaining walls over four feet tall (Section 12-B.020.A). The Public Works Director issues permits subject to conditions requiring the smallest practicable disturbed area, retention of natural vegetation where feasible, and prompt stabilization of disturbed soil (Section 12-B.030). Submittal requirements under Section 12-B.040 include a re-vegetation plan with at least six inches of topsoil and native seed mix on all disturbed surfaces before final city acceptance (12-B.040.B.2), and, critically, 'a map of the subject area showing the location and type of erosion and sedimentation control devices,' with sediment fences, traps and basins constructed 'before other land-disturbing activities occur' and 'properly maintained, regularly inspected, and cleaned as necessary' (Section 12-B.040.L).

Applicants must also submit a current Storm Water Pollution Prevention Plan (SWPPP) and a Utah State Notice of Intent (NOI), maintained for the life of the permit (Section 12-B.040.Q). Grading near waterways additionally requires a Stream Alteration Permit from the Utah Division of Water Rights (Section 12-B.040.R). A grading permit cannot run longer than one year without an extension under Development Code Section 10.120. Public utility, park and road projects, cemetery graves, and routine landscape maintenance of already-established landscaping are exempt (Section 12-B.020.B), but an exemption from the grading permit does not excuse compliance with any other applicable city code (Section 12-B.020.C).

Violations & Fines

Work not performed in compliance with the SWPPP plan is a grading permit violation (Section 12-B.080.G), as is grading outside the approved surveyed area, removal of survey stakes, or hauling off approved routes. Grading without a valid permit or after a permit expires draws a minimum daily fine of $500 per day (Section 12-B.090.D), and repeated out-of-bounds grading triggers escalating stop-work orders, a 30-day grading ban, and eventual permit revocation requiring a new permit fee and bond (Section 12-B.090.A). Violations may also be charged as a misdemeanor under Section 34.010 (Section 12-B.090.E).

Frequently Asked Questions

When does Lehi require a grading permit for erosion control?
A grading permit is required once a project disturbs more than one acre through grading, clearing or grubbing, or changes site elevation more than two feet from adjacent properties, per Development Code Section 12-B.020.A. Retaining walls over four feet tall also trigger the permit requirement regardless of disturbed acreage.
What erosion control measures does Lehi require on a permitted grading site?
Section 12-B.040.L requires a map showing erosion and sedimentation control devices, with sediment fences, traps and basins constructed before other land-disturbing activities start. Those devices must be properly maintained, regularly inspected, and cleaned, with removed sediment disposed of where it cannot flow back into the control structure.
Does Lehi require a stormwater plan in addition to erosion controls?
Yes. Section 12-B.040.Q requires a current Storm Water Pollution Prevention Plan (SWPPP) and a Utah State Notice of Intent (NOI), both maintained throughout the permit period. Failing to work in compliance with the SWPPP is itself listed as a grading permit violation under Section 12-B.080.G.
What happens if grading occurs without a permit in Lehi?
Unpermitted grading, or grading after a permit expires, draws a minimum fine of $500 per day under Section 12-B.090.D and can be charged as a misdemeanor under Section 34.010. Grading outside the approved surveyed area also triggers a stop-work order until the site is restored to its original elevation and re-vegetated.

Sources & Official References

Other rules in Lehi

All Lehi rules

Compare Lehi to another location·View the Utah environmental rules overview

Get notified when Erosion Control in Lehi, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.