Eagle Mountain, UT Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Plan required
For all construction land disturbance (13.75.110(H))
Certification
Sealed by a Utah licensed professional engineer
Street debris
Remove by end of work day
Late removal
Deemed a violation of the chapter
Penalty
$50.00 to $5,000 per day (EMMC 13.75.170)
Enforcement
City engineer, stop-work orders (13.75.160)

Summary

Eagle Mountain requires a sealed sediment and erosion control plan for every construction activity that disturbs land, under EMMC 13.75.110(H). The plan must be prepared by a registered professional engineer licensed in Utah, describe the site's erosion risks, and detail control measures, and any soil or debris tracked onto streets must be cleared by the end of the work day.

H. Sediment and Erosion Control Plans. The applicant must prepare a sediment and erosion control plan for all construction activities. The sediment and erosion control plan shall accurately describe the potential for soil erosion and sedimentation problems resulting from land disturbing activity and shall explain and illustrate the measures that are to be taken to control these problems. ... The plan shall be sealed by a registered professional engineer licensed in the state of Utah. ... ... 15. Specific details for: the construction of rock pads, wash down pads, and settling basins for controlling erosion; road access points; eliminating or keeping soil, sediment, and debris on streets and public ways at a level acceptable to the city engineer. Soil, sediment, and debris brought onto streets and public ways must be removed by the end of the work day by machine, broom or shovel to the satisfaction of the city engineer. Failure to remove the sediment, soil or debris shall be deemed a violation of this chapter.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance O-34-2026, passed August 4, 2026).

Full Breakdown

110(H) requires every applicant undertaking construction activity to prepare a sediment and erosion control plan that accurately describes the potential for soil erosion and sedimentation problems the land disturbing activity could cause and explains and illustrates the measures that will control them. The plan's length and complexity must match the size of the project, the severity of site conditions, and the potential for off-site damage, and it must be sealed by a registered professional engineer licensed in the state of Utah and conform to the city's BMP manual.

The ordinance lists specific required content: a project description with unit and structure counts, a topographic map with five-foot or smaller contour intervals showing existing and proposed conditions, all existing drainage ways including intermittent and wet-weather channels and any floodways or flood plains, a description of existing land cover, and identification of tree stands to be preserved versus removed, with tree protection measures shown to scale. The plan must also show the approximate limits of clearing, grading, and filling; existing and post-construction storm water flows leaving the site, including effects on adjoining property and the capacity of receiving waterways; the projected construction sequence tied to grading and drainage work; and specific remediation measures, including detailed drawings of temporary and permanent stabilization measures with a maintenance schedule.

Item 15 imposes a day-to-day housekeeping duty: soil, sediment, and debris brought onto streets and public ways must be eliminated or kept at a level acceptable to the city engineer, and any such material tracked onto a street must be removed by the end of the work day by machine, broom, or shovel to the city engineer's satisfaction. Failing to remove that sediment, soil, or debris is itself deemed a violation of the storm water chapter.

Violations & Fines

Failing to remove sediment, soil, or debris tracked onto streets and public ways by the end of the work day is deemed a violation of EMMC Chapter 13.75. The city engineer enforces the erosion control plan requirement under EMMC 13.75.160 with notices of violation and stop-work orders, and EMMC 13.75.170 sets a civil fine of $50.00 to $5,000 per day, each day a separate violation, appealable to the city council within 15 days.

Frequently Asked Questions

Does Eagle Mountain require an erosion control plan for construction?
Yes. EMMC 13.75.110(H) requires any applicant undertaking land disturbing construction activity to prepare a sediment and erosion control plan describing the erosion and sedimentation risks and the measures that will control them, sealed by a registered professional engineer licensed in Utah and conforming to the city's BMP manual.
What must an Eagle Mountain erosion control plan include?
The plan must include a project description, a topographic map with five-foot or smaller contour intervals, existing drainage ways and floodplains, existing land cover and tree preservation details, clearing and grading limits, pre- and post-construction storm water flows, the construction sequence, and specific stabilization measures with a maintenance schedule, all listed in EMMC 13.75.110(H).
What happens if construction debris is left on the street?
It is a violation. EMMC 13.75.110(H)(15) requires soil, sediment, and debris tracked onto streets and public ways to be removed by the end of the work day by machine, broom, or shovel to the city engineer's satisfaction, and failing to remove it is deemed a violation of the storm water chapter, EMMC Chapter 13.75.

Sources & Official References

Other rules in Eagle Mountain

All Eagle Mountain rules

Compare Eagle Mountain to another location·View the Utah environmental rules overview

Get notified when Erosion Control in Eagle Mountain, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Utah County handle erosion control.

Orem, UT
Some Restrictions
Provo, UT
Some Restrictions
Lehi, UT
Some Restrictions