Orem, UT Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
500+ sq ft of land disturbance
Stabilization deadline
Within 14 days of work stopping
Bond, up to 100 ft frontage
$4,000
Bond, over 300 ft frontage
$10,000
Single-lot bond
$1,000, released at stabilization
Street cleanup window
24 hours for mud/dirt/debris
Approving official
Storm Water Division Manager

Summary

Orem requires a Land Disturbance Permit before any activity disturbing 500 or more square feet of land, backed by a Storm Water Pollution Prevention Plan. Disturbed soil must be stabilized within 14 days after work stops, and applicants post a bond scaled to the site's street frontage.

A Land Disturbance Permit (or "Permit") is required before any person may perform any type of land disturbance activity that will disrupt or cause a change in the natural landscape upon any parcel of property located in the City. ... Land disturbance activities disturbing less than 500 square feet of land surface area [are exempt]. ... Stabilization measures shall be initiated as soon as practicable in disturbed portions of the site where land disturbance activities have temporarily or permanently ceased, but in no case more than 14 days after the land disturbance activity in that portion of the site has temporarily or permanently ceased, except under the following circumstances: If the initiation of stabilization measures by the 14th day after land disturbance activity temporarily or permanently ceases is precluded by snow cover or frozen ground conditions, stabilization measures shall be initiated as soon as practicable.

Full Breakdown

Orem City Code Section 23-4-7 targets sediment and construction pollutants leaving building sites before they reach the storm water system. A Land Disturbance Permit is required before disrupting or changing the natural landscape on any parcel, with exemptions for emergency utility or City work, disturbances under 500 square feet, residential gardening, bona fide farming that is the parcel's principal use, and sites that already hold a state Notice of Intent. Applicants file with Development Services and submit a Storm Water Pollution Prevention Plan (SWPPP) describing the site, the sequence of soil-disturbing activities, and specific control measures, including Best Management Practices and, where possible, low-impact development techniques.

Disturbed portions of a site must be stabilized, through seeding, mulching, geo-textiles, or similar measures, as soon as practicable and no later than 14 days after disturbance activity stops in that portion, except when snow or frozen ground delays it or work will resume within 21 days. Applications are due on or before the applicant's preliminary subdivision plat, site plan, conditional use permit, or building permit filing, and moving dirt before the permit issues is unlawful. A bond is required: $4,000 for up to 100 feet of street frontage, $6,000 up to 200 feet, $8,000 up to 300 feet, $10,000 beyond that, or a flat $1,000 for single lots in a common plan of development, released at final site stabilization.

The Storm Water Division Manager approves, conditions, or denies the permit, and denials may be appealed to the City Manager. Covering a curb, gutter, or sidewalk with mud or debris and leaving it overnight, and washing vehicles so concrete or mud reaches a street or the storm system, are separately prohibited and treated as nuisances regardless of permit status.

Violations & Fines

Tracked mud, dirt, or debris on a public or private street must be removed within 24 hours; leaving it is both a code violation and a nuisance enforceable under Articles 11-1 and 23-5, against the driver and the general contractor or job-site owner alike. Enforcement follows Article 23-5: a Notice of Violation, an administrative citation with a fine set by City Council resolution, or criminal prosecution. The City may also draw on the Public Improvement and Repair Bond to cover cleanup costs plus an administrative charge, and a third violation can bring a Stop Work Order.

Frequently Asked Questions

When does Orem require a Land Disturbance Permit?
Before disturbing 500 or more square feet of land surface, per Orem City Code 23-4-7(2). Smaller disturbances, residential gardening, bona fide farming, and emergency utility work are exempt, as are sites already holding a state construction Notice of Intent.
How quickly must disturbed soil be stabilized?
No later than 14 days after land disturbance activity temporarily or permanently stops on that part of the site, using measures like seeding, mulching, or geo-textiles, unless snow or frozen ground makes that impossible or work resumes within 21 days.
How much is the erosion control bond in Orem?
It scales with street frontage: $4,000 up to 100 feet, $6,000 up to 200 feet, $8,000 up to 300 feet, and $10,000 beyond that, or a flat $1,000 for a single lot in a common development plan, refunded once the site is stabilized.
What if a contractor tracks mud onto the street?
It must be cleaned up within 24 hours under Section 23-4-7(9); leaving it longer is a violation and a nuisance, and the City can bill cleanup costs against the contractor's Public Improvement and Repair Bond or issue a citation.

Sources & Official References

Other rules in Orem

All Orem rules

Compare Orem to another location·View the Utah environmental rules overview

Get notified when Erosion Control in Orem, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.