Key Facts

Permit required
Storm Water Connection Permit, direct or indirect
Reviewing body
Development Review Committee
Appeal path
City Manager
Single-family exemption
Only if per approved plat/site plan
Criminal penalty
Class C misdemeanor
3rd violation
Stop Work Order may issue

Summary

Orem makes it unlawful to obstruct, cover, or contribute to blocking any part of the City's storm water system, including drain inlets. Anyone connecting to that system, directly by pipe or indirectly through a sump, must first get a Storm Water Connection Permit from the City, reviewed by the Development Review Committee.

Unlawful Obstructions. It is unlawful for any person to: Obstruct the flow of water in the storm water system. Contribute to the obstruction of the flow of water in the storm water system. Cover or obstruct any drain inlet. ... Permit Required. Except as provided for in Section 23-4-7, no person shall connect to the City's storm water system without first obtaining a Storm Water Connection Permit (Permit) from the City. The requirement to obtain a Storm Water Connection Permit applies to direct connections to the storm water system (e.g. a piped connection to a piped portion of the storm water system) and indirect connections to the storm water system (e.g. discharges to sumps). The Storm Water Connection Permit described in this Section is a long-term permit designed to protect the storm water system, and is separate and distinct from the shorter term Land Disturbance Permit described in Section 23-4-7.

Full Breakdown

Orem City Code Article 23-3 governs the municipal storm water system (the MS4). Section 23-3-2 bars obstructing the flow of water in the system or covering a drain inlet, with narrow exceptions for City-authorized street or flood-control work. Section 23-3-4 requires a Storm Water Connection Permit before any direct or indirect connection, separate from the shorter-term Land Disturbance Permit used during construction under Section 23-4-7. Detached single-family homes are exempt only if runoff is handled per an approved plat or site plan; adding a basement pump or foundation drain not shown on that plan still triggers the permit requirement.

Applicants file with the Development Services Department and must submit a Best Management Practices (BMP) plan, a maintenance plan, engineer-stamped drawings of permanent storm water improvements, and a fee set by City Council resolution. The BMP plan must provide for pretreatment unless the Development Review Committee (DRC) agrees it is unnecessary, and only preferred BMPs listed on the City's website may be used unless the Storm Water Division Manager approves an alternate. The DRC approves, conditions, or denies the permit; either the applicant or the City may appeal that decision to the City Manager.

Once connected, the permit holder must supply as-built plans, and failing to build or maintain the approved improvements is itself a violation enforceable under Article 23-5. Article 23-3 also gives the Director authority to inspect via easements, require monitoring and analysis if a site is causing storm water pollution, and bars removing or altering system components, or opening a storm water manhole, without written permission.

Violations & Fines

Violations of Chapter 23 are enforced under Article 23-5: the City may issue a Notice of Violation, an administrative citation carrying a fine set by City Council resolution (with higher fines for repeats within 12 months), or pursue criminal prosecution. Each day a violation continues is a separate offense, and a third violation can trigger a Stop Work Order alongside the citation. Violations of this Chapter are class C misdemeanors, and the City may prosecute immediately if the violator has a prior offense, the violation poses a serious hazard, or it is treated as an emergency.

Frequently Asked Questions

Do I need a permit to connect to Orem's storm drain system?
Yes. Orem City Code 23-3-4 requires a Storm Water Connection Permit from the City before any direct piped connection or indirect connection such as a sump discharge, unless you fall under a narrow exemption like an already-approved single-family site plan.
Can I cover a storm drain inlet on my property?
No. Section 23-3-2 makes it unlawful to obstruct the flow of water in the storm water system or cover or obstruct any drain inlet, except for City-authorized street, flood-control, or approved cleanup work.
What does the Storm Water Connection Permit application require?
An application form, a Best Management Practices plan, a maintenance plan, engineer-stamped plans of the permanent storm water improvements, and a fee set by City Council resolution, all reviewed by the Development Review Committee.
What happens if I don't maintain my approved storm water improvements?
Failing to construct or maintain them as approved is a violation under Article 23-5, which can bring a Notice of Violation, an administrative citation with a fine, or criminal prosecution as a class C misdemeanor for repeated or serious cases.

Sources & Official References

Other rules in Orem

All Orem rules

Compare Orem to another location·View the Utah environmental rules overview

Get notified when Stormwater Management in Orem, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Nearby Cities

How other cities in Utah County handle stormwater management.

Eagle Mountain, UT
Some Restrictions
Provo, UT
Some Restrictions
Lehi, UT