Key Facts

Elevation data required
Lowest floor elevation relative to mean sea level
Who reviews it
Floodplain administrator (city building official)
Variance below BFE
Requires written insurance-risk notice, EMMC 15.105.040(J)(3)
Small-lot variance
Available on lots of one-half acre or less
Floodway limit
No variance if it raises base flood levels
Penalty for noncompliance
Up to $1,000 fine and/or 30 days jail

Summary

Eagle Mountain's floodplain administrator, the city building official, requires a building permit applicant to document the elevation of the lowest floor of new and substantially improved structures under EMMC 15.105.030(C). Where a variance allows a structure's lowest floor to sit below the base flood elevation, EMMC 15.105.040(J)(3) requires written notice of the added flood insurance risk.

Application for a building permit shall be presented to the floodplain administrator on forms furnished by him/her and may include, but not be limited to, plans in duplicate drawn to scale showing the location, dimensions, and elevation of proposed landscape alterations, existing and proposed structures, including the placement of manufactured homes, and the location of the foregoing in relation to areas of special flood hazard when defined. ... Elevation (in relation to mean sea level) of the lowest floor (including basement) of all new and substantially improved structures; ... Any applicant to whom a variance is granted shall be given written notice that the structure will be permitted to be built with the lowest floor elevation below the base flood elevation, and that the cost of flood insurance will be commensurate with the increased risk resulting from the reduced lowest floor elevation.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance O-34-2026, passed August 4, 2026).

Full Breakdown

Eagle Mountain does not set a blanket freeboard number in Chapter 15.105 EMMC, but it does require elevation documentation and disclosure tied to the base flood elevation. Under EMMC 15.105.030(C)(1), an application for a building permit goes to the floodplain administrator, the city building official under EMMC 15.105.030(A), with plans showing the location, dimensions, and elevation of proposed structures and any landscape alterations relative to the area of special flood hazard. When requested, the applicant must provide the elevation, in relation to mean sea level, of the lowest floor, including any basement, of all new and substantially improved structures, the elevation to which any nonresidential structure will be flood-proofed, and a registered engineer's or architect's certificate that a flood-proofed nonresidential structure meets the standards in EMMC 15.105.050.

The base flood elevation becomes decisive when a property owner seeks a variance. EMMC 15.105.040 lets the planning commission, sitting as the appeal board, grant variances from the chapter's requirements, but EMMC 15.105.040(J)(3) requires that any applicant who receives a variance get written notice that the structure will be permitted with its lowest floor elevation below the base flood elevation, and that flood insurance will cost more because of that added risk. Variances for a lot of one-half acre or less surrounded by existing below-base-flood structures are available under EMMC 15.105.040(F), but the appeal board cannot issue a variance within a mapped floodway if it would raise flood levels during the base flood, per EMMC 15.105.040(H).

Violations & Fines

A structure built without documenting its lowest floor elevation as required by EMMC 15.105.030(C), or built below the base flood elevation without a variance and the written insurance-risk notice required by EMMC 15.105.040(J)(3), is out of compliance with Chapter 15.105 EMMC. EMMC 15.105.060 makes noncompliant construction a misdemeanor, fined up to $1,000, jailed up to 30 days, or both, per violation, plus the city's costs.

Frequently Asked Questions

Does Eagle Mountain require a specific freeboard above base flood elevation?
Chapter 15.105 EMMC does not set a numeric freeboard requirement. It instead requires the floodplain administrator to collect the lowest floor elevation of new and substantially improved structures under EMMC 15.105.030(C)(1)(a) and, if a variance later allows construction below the base flood elevation, requires written notice of that fact under EMMC 15.105.040(J)(3).
What must my building permit application show about flood elevation?
Under EMMC 15.105.030(C), the floodplain administrator can require the elevation, relative to mean sea level, of the lowest floor including any basement, the flood-proofing elevation for nonresidential structures, and an engineer's or architect's certificate confirming compliance with the flood-proofing standards in EMMC 15.105.050.
Can I get a variance to build below the base flood elevation?
Only from the planning commission acting as the appeal board, and only after showing good cause and exceptional hardship under EMMC 15.105.040(J). If granted, EMMC 15.105.040(J)(3) requires written notice that flood insurance will cost more because the lowest floor sits below the base flood elevation.

Sources & Official References

Other rules in Eagle Mountain

All Eagle Mountain rules

Compare Eagle Mountain to another location·View the Utah environmental rules overview

Get notified when Flood Elevation Requirements in Eagle Mountain, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Utah County handle flood elevation requirements.

Orem, UT
Some Restrictions
Provo, UT
Some Restrictions
Lehi, UT
Significant Restrictions