Lehi, UT Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard minimum
- 1 foot above BFE
- Applies to
- Lowest floor incl. basement
- Certification required from
- Engineer, architect, or surveyor
- Crawlspace grade limit
- 2 feet below LAG
- Flood vent sizing
- 1 sq in per sq ft
Summary
New and substantially improved homes in Lehi's mapped flood zones must have their lowest floor, including any basement, elevated at least one foot above the base flood elevation, with a certified elevation submitted to the city.
B.1. Residential Construction for Zones A1-30, A, AE. New construction and substantial improvement of any residential structure shall have the lowest floor (including basement) elevated to one foot above the BFE. If a freeboard option is noted, new construction and substantial improvement shall have the lowest floor (including basement) elevated to the freeboard elevation. A registered professional engineer, architect, or land surveyor shall submit certified elevations to the Floodplain Administrator that the standards of this chapter are satisfied.
Full Breakdown
1 of the Lehi City Development Code sets the elevation floor for residential construction in Zones A1-30, A, and AE: the lowest floor, including a basement, must sit at least one foot above the Base Flood Elevation (BFE), and where a freeboard option applies, it must instead reach the higher freeboard elevation. A registered professional engineer, architect, or land surveyor must submit certified elevation data to the Floodplain Administrator confirming compliance before the structure is approved. 2 sets a parallel one-foot-above-BFE standard for nonresidential construction, or, as an alternative, requires the space below the BFE be built watertight with walls substantially impermeable to water and structural components able to resist hydrostatic and hydrodynamic loads, certified by a registered engineer or architect.
5. Crawlspace foundations below the BFE are capped: the interior grade cannot sit more than two feet below the Lowest Adjacent Grade, and the crawlspace height from floor to the next joist cannot exceed four feet, with flood vent openings sized at a minimum of one square inch per square foot of enclosed area to equalize hydrostatic pressure. The chapter's own definitions section describes freeboard as the added safety margin above the calculated flood level meant to cover unknowns like wave action and watershed urbanization that a bare BFE calculation does not capture.
Violations & Fines
Constructing or substantially improving a structure below the required one-foot freeboard elevation without the certified elevation documentation is a Floodplain Development Permit violation under Chapter 12-D, a Class B Misdemeanor carrying a fine of up to $1,000 and up to 180 days in jail per Section 12-D.030.J, and buildings lacking the elevation certificate are presumed noncompliant until it is produced.
Frequently Asked Questions
How high above the flood line must a Lehi home be built?
Can a commercial building in a flood zone skip the elevation requirement?
Are crawlspaces allowed below the flood elevation?
Sources & Official References
Other rules in Lehi
Compare Lehi to another location·View the Utah environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Utah County handle flood elevation requirements.