Key Facts

ITC duration cap
5 minutes on major roads
ITC frequency cap
once per 20 minutes
Traffic control agency
Woodland Police Department only
Double centerline detours
need City Engineer/Public Works approval
Signage standard
Caltrans Manual of Traffic Controls
Application lead time
5 working days if traffic affected

Summary

In the City of Woodland, California, filming permits that need interim traffic control on public streets must use the Woodland Police Department under Woodland Municipal Code § 9.32.010(G)(2). Interim traffic control on major roads is capped at five minutes and cannot recur more than once every 20 minutes, with the production company paying the officer costs.

G. Permit Conditions. ... 2. Traffic Control. Production companies must use the City Police Department for any filming that requires interim traffic control ("ITC"). ITC on major roads is limited to five minutes. ITC shall not occur more than once during any 20-minute period. The permittee is responsible for obtaining, and paying the cost of, the required officers. The following conditions shall apply: a. The permittee shall furnish and install all advance warning signs and any other traffic control devices in conformance with Caltrans' Manual of Traffic Controls for construction and maintenance work zones. b. Traffic shall not be detoured across a double centerline without prior approval of the City Engineer/Public Works Director.

Full Breakdown

Section 9.32.010(G) lets the City Filming Permit Coordinator attach conditions to a filming permit, and item 2, Traffic Control, governs any street work tied to a production. Production companies must use the Woodland Police Department, not a private traffic control firm, for interim traffic control (ITC), and they pay the full cost of the officers assigned. ITC on major roads is capped at five minutes at a time and cannot repeat more than once during any 20-minute period, which forces productions to plan takes around that cycle.

Subsection (a) requires permittees to furnish and install advance warning signs and traffic control devices that conform to Caltrans' Manual of Traffic Controls for construction and maintenance work zones, and subsection (b) bars detouring traffic across a double centerline without prior approval from the City Engineer or Public Works Director. Other conditions in the same list keep camera cars moving with traffic, require stationary in-lane cameras to be disclosed on the permit, forbid bagging or removing existing regulatory or warning signs without City approval, and require a wetted roadway to dry to the City's satisfaction before the set can strike. Applications affecting traffic or public safety must be filed at least five working days ahead under § 9.32.010(E)(1), longer than the standard three-day minimum.

Violations & Fines

Conducting interim traffic control without going through the Woodland Police Department, or violating the five-minute/20-minute ITC limits, is a misdemeanor under § 9.32.010(N), punishable per § 1.08.070. The Permit Coordinator may also deny a permit under § 9.32.010(F)(1) if the production would unduly interfere with traffic, or revoke an issued permit under § 9.32.010(M) for noncompliance with traffic-control conditions.

Frequently Asked Questions

Who handles traffic control for filming in Woodland?
Woodland Municipal Code § 9.32.010(G)(2) requires production companies to use the Woodland Police Department for any filming that needs interim traffic control, and the permittee pays the full cost of the officers assigned rather than hiring an outside traffic control company.
How long can a Woodland filming permit close or control a major road?
Interim traffic control on major roads is limited to five minutes at a time under § 9.32.010(G)(2), and it cannot repeat more than once during any 20-minute period, so productions have to plan repeated takes around that cycle.
Can filming vehicles cross a double centerline in Woodland?
No. Section 9.32.010(G)(2)(b) prohibits detouring traffic across a double centerline unless the City Engineer or Public Works Director approves it in advance, and any signage used must conform to Caltrans' Manual of Traffic Controls for work zones.

Sources & Official References

Other rules in Woodland

All Woodland rules

California rules heatmap·Compare Woodland to another location·View the California filming & production overview

Get notified when Street Closures in Woodland, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.