Key Facts

Trigger
Declaration of a hurricane warning (Sec. 19-170)
Solid waste
Must be removed or secured
Materials
Tied, banded, or netted down
'Secured' defined
Fastened covering/netting per the section
Baseline rule
Year-round site cleanliness (Sec. 19-169)

Summary

Once the city declares a hurricane warning, Sec. 19-170 requires every active construction site to either remove all stored solid waste or secure it against becoming wind-borne debris, and to tie, band, or net down any stored construction materials so wind can't turn a job site into flying debris.

(1)Upon declaration of a hurricane warning, all solid waste stored upon a construction site shall be removed from the site and disposed of in an approved manner or secured in such a manner as to prevent the waste material from becoming wind-borne debris during a storm.(2)Alternatively, upon declaration of a hurricane warning, construction materials stored on site shall be tied, banded, or placed within secured containers on the ground so as to prevent the materials from becoming wind-borne debris. For the purposes of this section, "secured" shall mean a protective covering or netting adequately sized and fastened on the ground to prevent waste materials and construction materials from becoming wind-borne debris.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 72 Update 1).

Full Breakdown

Section 19-170 targets the specific hazard of an active construction site during a storm: loose lumber, debris, and building materials that a hurricane can turn into projectiles. Once a hurricane warning is declared, subsection (1) requires that all solid waste stored on the site be removed and disposed of in an approved manner, or secured so it cannot become wind-borne debris during the storm. Subsection (2) covers construction materials that are staying on site: they must be tied, banded, or placed in secured containers on the ground, and the section defines 'secured' specifically as a protective covering or netting that is adequately sized and fastened to the ground.

This sits alongside the year-round site-debris rule in Sec. 19-169, which already requires every construction site to stay clean and sanitary, provide enough solid waste containers or a roll-off dumpster for the volume generated between pickups, and lets the building official stop work if a site isn't kept clean. Sec. 19-170 layers the storm-specific securing duty on top of that baseline the moment a hurricane warning is declared, shifting the obligation from routine housekeeping to active storm preparation, and it applies to any contractor or owner with an open permit and material staged on the property, not just to occupied buildings.

Violations & Fines

Failing to secure or remove site debris after a hurricane warning is declared is enforced the same way as any other building-code violation: a misdemeanor under Sec. 19-199, with each day the unsecured debris remains a separate offense. The building official can also issue a written stop-work order under Sec. 19-206, and under Sec. 19-169 can already order work stopped for a construction site that isn't kept in a clean, sanitary condition even before a storm is declared.

Frequently Asked Questions

What does my contractor have to do with debris once a hurricane warning goes out?
Section 19-170(1) requires that all solid waste stored on the construction site be removed from the site and disposed of in an approved manner, or secured so it can't become wind-borne debris, as soon as a hurricane warning is declared.
Can I just leave lumber stacked on my job site during a storm?
No. Section 19-170(2) requires construction materials left on site to be tied, banded, or placed in secured containers on the ground, and defines 'secured' as a protective covering or netting adequately sized and fastened to the ground to keep the material from becoming wind-borne debris.
Is there a debris rule for construction sites outside of hurricane season?
Yes. Section 19-169 requires every active construction site to stay clean and sanitary year-round, with enough solid waste containers or an approved roll-off dumpster to handle debris between scheduled pickups, and the building official can stop work if a site isn't kept that way.

Sources & Official References

Other rules in Boca Raton

All Boca Raton rules

Florida rules heatmap·Compare Boca Raton to another location·View the Florida hurricane preparedness overview

Get notified when Storm Debris in Boca Raton, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Storm Debris in Nearby Cities

How other cities in Palm Beach County handle storm debris.

Boynton Beach, FL
Some Restrictions
West Palm Beach, FL
Some Restrictions